Adopted on 27 March Juche 91 (2002) by Ordinance No. 12 of the Supreme People’s Assembly
Amended and supplemented on 26 October Juche 93 (2004) by Decree No. 742 of the Standing Committee of the Supreme People’s Assembly
Source · Republic of Korea National Intelligence Service, Compilation of North Korean Laws (북한법령집), August 2024, vol. 1, pp. 702–707.
The first draft of this translation was produced with AI assistance.
Chapter 1. Fundamentals of the Land Planning Law
Section titled “Chapter 1. Fundamentals of the Land Planning Law”Article 1 (Mission of the Land Planning Law)
Section titled “Article 1 (Mission of the Land Planning Law)”The Land Planning Law of the Democratic People’s Republic of Korea contributes to carrying out land management in a planned manner by strictly establishing the system and order in the drawing up, endorsement and implementation of land plans.
Article 2 (Classification of land plans)
Section titled “Article 2 (Classification of land plans)”A land plan is a unified and comprehensive long-term plan concerning the management of land, resources and the environment.
Land plans include the nationwide master plan for land construction, the master plans for land construction of important districts, the master plans for land construction of provinces (municipalities directly under central authority), and the master plans for land construction of cities (districts) and counties.
Article 3 (Principle of drawing up land plans)
Section titled “Article 3 (Principle of drawing up land plans)”Drawing up land plans correctly is the fundamental guarantee for remaking nature, building creations for ten thousand years and providing the people with a fine living environment.
The State shall ensure that centralized and unified guidance is firmly provided in drawing up land plans while the creative initiative of subordinate units is fully displayed.
Article 4 (Principle of endorsement of land plans)
Section titled “Article 4 (Principle of endorsement of land plans)”Endorsement of a land plan is an important undertaking that deliberates on and approves the plan that has been drawn up.
The State shall ensure scientific character and realism in the deliberation and approval of land plans.
Article 5 (Principle of implementation of land plans)
Section titled “Article 5 (Principle of implementation of land plans)”Thoroughly implementing land plans is the basic way to transform the appearance of the land.
The State shall ensure that land management such as land consolidation, afforestation, construction of residential districts and industrial districts, road construction, resource development and environmental protection is carried out in strict conformity with the land plan.
Article 6 (Principle of drawing up and implementing capital construction plans and designs)
Section titled “Article 6 (Principle of drawing up and implementing capital construction plans and designs)”A land plan is the basis for drawing up capital construction plans and designs.
The State shall ensure that capital construction plans and designs are drawn up and implemented in keeping with the land plan.
Article 7 (Principle of land management by the whole people)
Section titled “Article 7 (Principle of land management by the whole people)”The State shall properly establish the system of land planning work and strengthen education in socialist patriotism among the people, so as to ensure that they cherish and love the land and actively take part in land management work.
Article 8 (Principle of training technicians and specialists in the land planning sector)
Section titled “Article 8 (Principle of training technicians and specialists in the land planning sector)”The State shall ensure that technicians and specialists in the land planning sector are trained with a long-term view in keeping with the requirements of the information industry era, and that land planning work is modernized and put on a scientific basis.
Article 9 (Exchange and cooperation in the land planning sector)
Section titled “Article 9 (Exchange and cooperation in the land planning sector)”The State shall ensure that exchange and cooperation with other countries and international organizations are strengthened in the land planning sector.
Chapter 2. Drawing up of land plans
Section titled “Chapter 2. Drawing up of land plans”Article 10 (Organs that draw up land plans)
Section titled “Article 10 (Organs that draw up land plans)”Drawing up a land plan is the first stage of land planning work.
The nationwide master plan for land construction and the master plans for land construction of important districts shall be drawn up by the central land and environment protection guidance organ, and the master plans for land construction of provinces (municipalities directly under central authority), cities (districts) and counties by the land and environment protection organ of the province (municipality directly under central authority).
Article 11 (Principles to be observed in drawing up land plans)
Section titled “Article 11 (Principles to be observed in drawing up land plans)”The principles to be observed in drawing up land plans are as follows:
- Arable land shall not be encroached upon.
- The size of cities shall not be made too large.
- The climatic and natural characteristics of the area concerned shall be taken into account.
- The prospects of economic development and practical benefit shall be assessed.
- The requirements of national defence shall be taken into account.
- The environment shall not be destroyed.
Article 12 (Prospective period of land plans)
Section titled “Article 12 (Prospective period of land plans)”The prospective period of a land plan is 50 years.
Where necessary, the prospective period of a land plan may be made shorter than 50 years.
Article 13 (Criterion for drawing up land plans)
Section titled “Article 13 (Criterion for drawing up land plans)”The criterion for drawing up land plans is the State’s land management policy.
The central land and environment protection guidance organ shall, on the basis of the State’s land management policy, set the tasks for drawing up land plans, prepare a guidance manual and send it down to the relevant institutions.
Article 14 (Surveying and keeping track of the land situation)
Section titled “Article 14 (Surveying and keeping track of the land situation)”A land plan may not be drawn up without surveying and keeping track of the land situation.
The land and environment protection organ shall survey and keep track of the land situation necessary for drawing up land plans.
Article 15 (Provision of necessary information data)
Section titled “Article 15 (Provision of necessary information data)”The land and environment protection organ may request the data necessary for drawing up land plans from the relevant institutions, enterprises and organizations.
Institutions, enterprises and organizations shall provide in good time the information data requested by the land and environment protection organ, such as the state of resources, population numbers, prospects of economic development, the state of construction, hydrometeorological forecasts and observation data, the state of the environment, satellite photographs and maps.
Article 16 (Drawing up of draft land plans)
Section titled “Article 16 (Drawing up of draft land plans)”The land and environment protection organ shall study and analyse the land situation and draw up the draft land plan. In this case it shall consult the organs concerned.
The draft land plan shall include such matters as the land development strategy, protection of revolutionary battle sites and revolutionary historic sites, use of arable land, forests, rivers, lakes and seas, resource development, formation of cities and villages, development of recreation districts, construction of industrial districts and infrastructure, creation and protection of the natural environment, and land tidying and beautification work.
Article 17 (Basis for drawing up master plans for land construction)
Section titled “Article 17 (Basis for drawing up master plans for land construction)”The nationwide master plan for land construction shall be drawn up taking into account such matters as prospects of economic and cultural development.
The master plans for land construction of important districts and of provinces (municipalities directly under central authority) shall be drawn up on the basis of the nationwide master plan for land construction, and the master plans for land construction of cities (districts) and counties on the basis of the master plan for land construction of the province (municipality directly under central authority).
Chapter 3. Endorsement of land plans
Section titled “Chapter 3. Endorsement of land plans”Article 18 (Basic requirement for endorsement of land plans)
Section titled “Article 18 (Basic requirement for endorsement of land plans)”Strictly observing the procedure for endorsement of land plans is an important condition for guaranteeing the correct implementation of land plans.
The land and environment protection organ shall submit the nationwide master plan for land construction and the master plans for land construction of important districts that it has drawn up to the Cabinet, and the master plans for land construction of provinces (municipalities directly under central authority), cities (districts) and counties to the people’s committee of the province (municipality directly under central authority).
Article 19 (Submission of master plans for land construction for endorsement)
Section titled “Article 19 (Submission of master plans for land construction for endorsement)”The Cabinet shall submit the nationwide master plan for land construction and the master plans for land construction of important districts for endorsement by the Supreme People’s Assembly or the Standing Committee of the Supreme People’s Assembly. In this case they shall be discussed at a plenary meeting or an executive meeting.
Article 20 (Deliberation and approval of the nationwide and important district master plans for land construction)
Section titled “Article 20 (Deliberation and approval of the nationwide and important district master plans for land construction)”The nationwide master plan for land construction and the master plans for land construction of important districts shall be deliberated on and approved by the Supreme People’s Assembly.
A master plan for land construction submitted during a recess of the Supreme People’s Assembly shall be deliberated on and approved by the Standing Committee of the Supreme People’s Assembly.
Article 21 (Deliberation and approval of other master plans for land construction)
Section titled “Article 21 (Deliberation and approval of other master plans for land construction)”The master plans for land construction of provinces (municipalities directly under central authority), cities (districts) and counties shall be deliberated on and approved by the people’s assembly of the province (municipality directly under central authority).
A master plan for land construction submitted during a recess of the people’s assembly of the province (municipality directly under central authority) shall be deliberated on and approved by the people’s committee of the province (municipality directly under central authority).
Article 22 (Handing down of endorsed land plans)
Section titled “Article 22 (Handing down of endorsed land plans)”The land and environment protection organ shall send down an endorsed land plan within one month to the relevant institutions, enterprises and organizations, including the State planning organ, the State construction supervision organ and local organs of power.
Chapter 4. Implementation of land plans
Section titled “Chapter 4. Implementation of land plans”Article 23 (Basic requirement for implementation of land plans)
Section titled “Article 23 (Basic requirement for implementation of land plans)”Implementation of land plans is great nature-remaking work for managing land, resources and the environment in keeping with the aspirations and demands of the people.
The land and environment protection organ and the relevant institutions, enterprises and organizations shall carry out land management in accordance with the land plan.
Article 24 (Fixing the order of implementation of land plans)
Section titled “Article 24 (Fixing the order of implementation of land plans)”Institutions, enterprises and organizations that have had a land plan handed down to them shall properly determine the immediate or long-term tasks for implementing the land plan and the order by year and by project.
Article 25 (Drawing up of technical tasks and master plans for construction)
Section titled “Article 25 (Drawing up of technical tasks and master plans for construction)”Institutions, enterprises and organizations that have received project tasks for implementing a land plan shall draw up technical tasks and master plans for construction.
The technical tasks and master plans for construction that have been drawn up shall obtain the agreement of the land and environment protection organ.
Article 26 (Submission of application documents for land construction and development)
Section titled “Article 26 (Submission of application documents for land construction and development)”An institution, enterprise or organization that intends to construct land or develop resources shall submit application documents to the land and environment protection organ. In this case documents such as a site survey report shall be attached.
The land and environment protection organ shall in good time report on the submitted application documents and approve or reject them.
Article 27 (Issue of the construction site designation document or the land development approval document)
Section titled “Article 27 (Issue of the construction site designation document or the land development approval document)”Where the land and environment protection organ has approved land construction or resource development, it shall issue a construction site designation document or a land development approval document.
A construction site designation document shall be issued in cases such as construction of buildings and structures, and a land development approval document in cases such as creation and development of resources, construction of cities and industrial districts, and designation of protected zones and special zones.
Article 28 (Projects for which no construction site designation document is issued)
Section titled “Article 28 (Projects for which no construction site designation document is issued)”No construction site designation document shall be issued for construction projects inside the area of a city or industrial district.
Article 29 (Construction specification, construction permit, land use permit and fund disbursement permit)
Section titled “Article 29 (Construction specification, construction permit, land use permit and fund disbursement permit)”A construction client institution, enterprise or organization shall, on the basis of the construction site designation document or the land development approval document, obtain such documents as a construction specification, construction permit, land use permit and fund disbursement permit. However, where it intends to develop resources or designate a protected zone, it need not obtain a construction specification.
Article 30 (Conditions for land construction and resource development)
Section titled “Article 30 (Conditions for land construction and resource development)”A construction client institution, enterprise or organization shall construct land or develop resources as specified in the construction site designation document or the land development approval document.
Where land construction or resource development has not been commenced within the prescribed period, the relevant approval shall be obtained again.
Article 31 (Construction of land plan projects and related facilities)
Section titled “Article 31 (Construction of land plan projects and related facilities)”The relevant institutions, enterprises and organizations shall construct land plan projects and their related facilities comprehensively. In this case they shall eliminate repeated work and shall not waste labour, materials and funds.
Article 32 (Reporting on the implementation of land plans)
Section titled “Article 32 (Reporting on the implementation of land plans)”An institution, enterprise or organization that has implemented a land plan shall report the status to the land and environment protection organ in good time.
The Cabinet and the land and environment protection organ shall regularly review the status of implementation of land plans.
Chapter 5. Guidance and control of land planning work
Section titled “Chapter 5. Guidance and control of land planning work”Article 33 (Basic requirement for guidance and control of land planning work)
Section titled “Article 33 (Basic requirement for guidance and control of land planning work)”Strengthening guidance and control of land planning work is a firm guarantee for correctly implementing the State’s land management policy.
The State shall ensure that, in keeping with the requirements of the development of reality, the system of guidance of land planning work is properly established and guidance and control are strengthened.
Article 34 (Guidance of land planning work)
Section titled “Article 34 (Guidance of land planning work)”Guidance of land planning work shall be exercised by the central land and environment protection guidance organ under the unified guidance of the Cabinet.
The central land and environment protection guidance organ shall provide guidance so that land plans are drawn up properly and carried out without fail.
Article 35 (Building of the land planning information base and reporting on changes in the situation)
Section titled “Article 35 (Building of the land planning information base and reporting on changes in the situation)”The central land and environment protection guidance organ shall firmly build a land planning information base capable of collecting, preserving and serving the data necessary for drawing up land plans.
The local land and environment protection organ shall regularly keep track of the changes in the state of the land and environment and report them to the central land and environment protection guidance organ.
Article 36 (Duty to observe master plans for land construction)
Section titled “Article 36 (Duty to observe master plans for land construction)”Local organs of power and the relevant institutions, enterprises and organizations shall carry out work such as land consolidation and river improvement, afforestation, and construction of roads and medium and small power stations in accordance with the master plan for land construction of the city (district) or county.
Article 37 (Provision of conditions for land planning work)
Section titled “Article 37 (Provision of conditions for land planning work)”The State planning organ, the labour administration organ and the relevant institutions shall ensure the timely supply of the labour, equipment, materials and funds necessary for the land planning sector.
The labour, equipment, materials and funds of the land planning sector may not be diverted to other sectors.
Article 38 (Supervision and control of land planning work)
Section titled “Article 38 (Supervision and control of land planning work)”Supervision and control of land planning work shall be exercised by the land and environment protection organ and the relevant supervision and control organ.
The land and environment protection organ and the relevant supervision and control organ shall strictly supervise and control land planning work.
Article 39 (Suspension)
Section titled “Article 39 (Suspension)”Acts such as constructing land or developing resources without approval shall be suspended.
Article 40 (Compensation for damage)
Section titled “Article 40 (Compensation for damage)”The person concerned shall be made to compensate for the damage caused by giving a construction specification or granting a land use permit contrary to the land plan.
Article 41 (Administrative or criminal liability)
Section titled “Article 41 (Administrative or criminal liability)”Administrative or criminal liability shall be imposed, according to the circumstances, on the officials responsible in an institution, enterprise or organization, and on individual citizens, who have violated this Law and thereby caused serious consequences for land planning work.