Law of the Democratic People's Republic of Korea on the Management of Railway Lines

Edition dated 17 January 2024. Korean source

Adopted on 2 February Juche 112 (2023) by Decree No. 1216 of the Standing Committee of the Supreme People’s Assembly
Amended and supplemented on 17 January Juche 113 (2024) by Decree No. 1530 of the Standing Committee of the Supreme People’s Assembly

Korean source · NK TechLab Korean PDF, archived copy. The text comes from unchecked OCR of screenshots from a North Korean law app. Publisher’s source description

This law covers the construction, protection, management and use of railway lines. See also the Railway Law.

The first draft of this translation was produced with AI assistance.

Chapter 1. Fundamentals of the Law on the Management of Railway Lines

Section titled “Chapter 1. Fundamentals of the Law on the Management of Railway Lines”

The Law of the Democratic People’s Republic of Korea on the Management of Railway Lines contributes to improving the cultured character and safety of railway lines and fully meeting the transport needs of the national economy by strictly establishing the system and order in the construction, protection and management, and use of railway lines.

In this Law, the following terms are defined as follows:

  1. A railway line is a way laid for trains to run on, consisting of a track bed, track and railway line structures.
  2. A track bed is the ground that supports the track.
  3. Track is the part comprising the rails, sleepers, fastenings and ballast layer.
  4. Railway line structures are the various facilities for protecting or maintaining a railway line, including railway bridges, tunnels, retaining walls and culverts.

Article 3 (Classification of railway lines)

Section titled “Article 3 (Classification of railway lines)”

Railway lines are classified by function as main lines, branch lines and dedicated lines, and by gauge as standard-gauge, narrow-gauge and broad-gauge lines.

The standard gauge of railway lines in our country is 1,435 mm.

Railway lines are classified as Class 1, Class 2, Class 3 or Class 4 according to their political and economic significance, annual freight volume and technical requirements.

Article 5 (Principle of modernizing railway lines)

Section titled “Article 5 (Principle of modernizing railway lines)”

Railway lines are the symbol of the railway. Upgrading the country’s railway lines is an important goal of railway modernization.

The State shall ensure that the country’s railway lines are upgraded for heavier loads and higher speeds.

Article 6 (Principle of care and management of railway lines by all the people)

Section titled “Article 6 (Principle of care and management of railway lines by all the people)”

Railway lines are the arteries of the country and an important component of the railway, which is the forerunner of the national economy.

The State shall strengthen education in patriotism among the people so that they cherish and care for railway lines, a valuable asset of the country, and take part in their management as masters.

Article 7 (Principle of strengthening scientific research)

Section titled “Article 7 (Principle of strengthening scientific research)”

The State shall ensure that scientific research and educational institutions in the railway transport sector are firmly established, that scientific research and training of technicians and specialists for higher loads and speeds are strengthened, and that advanced science, technology and construction methods are actively adopted in building, protecting and managing railway lines.

Article 8 (Principle of producing and providing railway line equipment)

Section titled “Article 8 (Principle of producing and providing railway line equipment)”

Producing and providing sufficient railway line equipment is an important condition for ensuring both the speed and the quality of railway line construction and protection.

The State shall ensure that modern production bases for railway line equipment are firmly established and that heavy rails, concrete sleepers, railway track fastenings and railway line construction equipment suited to the conditions of our country and meeting technical performance requirements are produced and provided as planned.

Article 9 (Principle of exchange and cooperation)

Section titled “Article 9 (Principle of exchange and cooperation)”

The State shall develop exchange and cooperation with other countries and international organizations in the field of railway lines.

Article 10 (Guidance of railway line management)

Section titled “Article 10 (Guidance of railway line management)”

Guidance of railway line management shall be exercised by the central railway transport guidance organ and local people’s committees under the unified guidance of the Cabinet.

The central railway transport guidance organ and local people’s committees shall establish the railway line management system and regularly take charge of and guide railway line management.

Article 11 (Railway line rating inspections)

Section titled “Article 11 (Railway line rating inspections)”

The central railway transport guidance organ and the relevant institutions shall organize railway line rating inspections twice a year and strictly review the defects found.

Article 12 (Supervision and control of railway line management)

Section titled “Article 12 (Supervision and control of railway line management)”

Supervision and control of railway line management shall be exercised by the central railway transport guidance organ and the relevant supervision and control organs.

The central railway transport guidance organ and the relevant supervision and control organs shall regularly supervise and control the construction, protection and management, and use of railway lines.

Article 13 (Scope of application of the Law)

Section titled “Article 13 (Scope of application of the Law)”

This Law applies to all institutions, enterprises, organizations and citizens within the territory of the Republic.

This Law also applies to institutions of other countries, foreign-invested enterprises and foreigners in our country.

Article 14 (Planning of railway line construction)

Section titled “Article 14 (Planning of railway line construction)”

Constructing the country’s railway lines scientifically and with a long-term view is an important requirement for increasing use of the railway.

The central railway transport guidance organ and local people’s committees shall carry out railway line construction according to plan in accordance with the master plan for national land construction.

Article 15 (Preparation of railway line construction plans)

Section titled “Article 15 (Preparation of railway line construction plans)”

A railway line construction plan shall be drawn up for laying a new line or technically upgrading an existing line.

Article 16 (Bodies responsible for preparing railway line construction plans)

Section titled “Article 16 (Bodies responsible for preparing railway line construction plans)”

Plans for new railway lines shall be drawn up by the central planning guidance organ. Plans for upgrading railway lines shall be drawn up by the relevant railway transport organ.

The bodies preparing the plans shall establish the proper priorities for railway line construction and draw up the plans so that construction is concentrated first on lines of great significance to the national economy.

Article 17 (Deliberation on railway line construction plans)

Section titled “Article 17 (Deliberation on railway line construction plans)”

A body preparing a railway line construction plan shall obtain the agreement of the relevant institutions and submit the plan for deliberation by the Cabinet or the central planning guidance organ, depending on the project.

The central planning guidance organ and the central railway transport guidance organ shall hand down approved railway line construction plans to railway line construction enterprises in good time.

Article 18 (Preparation of railway line construction designs)

Section titled “Article 18 (Preparation of railway line construction designs)”

Designs for building new railway lines or technically upgrading existing railway lines shall be prepared by railway design institutions in accordance with approved railway line construction plans.

Railway line construction designs shall be submitted for deliberation by the central railway transport guidance organ or the central design guidance organ, depending on the scale of investment and the project.

Article 20 (Construction of railway lines in accordance with designs)

Section titled “Article 20 (Construction of railway lines in accordance with designs)”

Railway line construction enterprises shall strictly observe the requirements of the designs in construction.

A railway line may not be constructed on the basis of an unapproved design.

Article 21 (Bodies responsible for railway line construction)

Section titled “Article 21 (Bodies responsible for railway line construction)”

State railway line construction shall be carried out by railway line construction enterprises under the central railway transport guidance organ and provincial railway construction enterprises.

Construction of a dedicated railway line shall be carried out by the relevant institution that will use the railway line exclusively.

Article 22 (Strengthening railway line construction capacity)

Section titled “Article 22 (Strengthening railway line construction capacity)”

Railway transport organs shall establish and strengthen a specialized construction workforce responsible for construction of the country’s railway lines.

The central planning guidance organ, the central labour administration guidance organ and the relevant institutions shall draw up annual plans for deploying the workers needed in the railway line construction sector and implement them accurately.

Article 23 (Compliance with technical regulations and standard construction methods)

Section titled “Article 23 (Compliance with technical regulations and standard construction methods)”

Railway line construction enterprises shall first build railway line structures, including bridges, tunnels and culverts, and shall strictly observe technical regulations and standard construction methods in construction, including building and compacting the track bed, laying ballast and sleepers, laying rails, installing fastenings, building retaining walls and digging drainage ditches.

Article 24 (Provision of railway line construction equipment)

Section titled “Article 24 (Provision of railway line construction equipment)”

Railway line construction enterprises shall equip themselves with modern equipment to achieve a high standard of speed and quality in railway line construction.

The Cabinet and the relevant institutions shall provide the conditions needed for railway line construction enterprises to acquire modern railway line construction equipment.

Article 25 (Quality inspection of construction projects)

Section titled “Article 25 (Quality inspection of construction projects)”

State construction supervision organs and railway transport organs shall strictly carry out in-process inspections, interim inspections and completion inspections in railway line construction so that construction quality is maintained at the highest standard.

If a project fails in-process or interim inspection, work on the next stage may not proceed. A railway line that fails completion inspection may not be handed over to the relevant institution.

Article 26 (Quality inspection of railway line equipment)

Section titled “Article 26 (Quality inspection of railway line equipment)”

The quality supervision organ shall strictly inspect the quality of rails, concrete sleepers and railway track fastenings.

Equipment that fails quality inspection may not be used in building or repairing railway lines.

Chapter 3. Protection and management of railway lines

Section titled “Chapter 3. Protection and management of railway lines”

Article 27 (Establishment of a system for protecting and managing railway lines)

Section titled “Article 27 (Establishment of a system for protecting and managing railway lines)”

The protection of railway lines is an important undertaking for improving their safety and cultured character.

Railway transport organs and local people’s committees shall establish an orderly system for protecting and managing railway lines and assign the relevant institutions, enterprises and organizations sections of line to manage on the principle of management by the square metre.

Article 28 (Survey of the condition of railway lines)

Section titled “Article 28 (Survey of the condition of railway lines)”

Railway transport organs shall regularly survey railway lines to detect in good time any defective railway lines or structures that pose a threat to the safe operation of trains and take the necessary measures. In this case, they shall properly establish survey priorities, conduct surveys in accordance with the relevant guide and provide the necessary data to institutions, enterprises and organizations assigned to manage sections of railway line so that they take measures.

Railway transport organs shall accurately enter survey data on the sections of railway line under their responsibility in the relevant form in the register of surveys of railway lines and structures.

The particulars and form of the register of surveys of railway lines and structures shall be as prescribed by the central railway transport guidance organ.

Article 30 (Technical inspection of railway lines)

Section titled “Article 30 (Technical inspection of railway lines)”

Railway transport organs shall organize technical inspections to assess the technical condition of railway lines scientifically and take measures for their repair, accurately draw up inspection plans by period and carry out detailed inspections of the railway lines and facilities in the sections under their responsibility.

Repairs to railway lines are classified as major, intermediate or minor according to the political and economic significance of the lines, annual freight volume, service life of equipment such as rails and sleepers, and the alignment and gradient of the railway lines.

Railway transport organs and the relevant institutions shall set proper railway line repair intervals and regularly carry out repairs in accordance with maintenance standards to ensure safe train operation.

Article 32 (Intensive repair of railway lines)

Section titled “Article 32 (Intensive repair of railway lines)”

Intensive repair periods shall be fixed for repairs in keeping with the technical condition of railway lines and changes in that condition by season.

Intensive repair periods shall be fixed by the central railway transport guidance organ.

Railway transport organs, local people’s committees and the relevant institutions shall fully mobilize workers, materials and means of transport and carry out intensive railway line repair during the seasonal intensive repair periods.

Article 33 (Handing down of railway line repair plans)

Section titled “Article 33 (Handing down of railway line repair plans)”

The central railway transport guidance organ, local people’s committees and the relevant institutions shall properly plan railway line repairs and provide the materials required under the plans so that repairs can be carried out fully and in good time.

Institutions and enterprises that receive railway line repair plans shall carry out repairs and report to the relevant institution once the repairs have passed inspection.

The relevant institutions and enterprises shall accurately calculate and pay the labour remuneration of persons mobilized for railway line repair and management.

Article 34 (Compulsory mobilization for damage recovery)

Section titled “Article 34 (Compulsory mobilization for damage recovery)”

Railway transport organs, local people’s committees and the relevant institutions, enterprises and organizations are required to mobilize the necessary workers, equipment and materials where recovery is required for damage to railway lines caused by disaster-causing abnormal weather or accidents.

Institutions, enterprises and organizations shall make thorough preparations in advance so that the necessary personnel and materials can be mobilized immediately for railway line recovery.

Railway transport organs shall assign patrol workers by designated sections so that the safety of railway lines is regularly checked and problems that arise are addressed in good time.

Railway patrol workers shall check the condition of railway lines in their designated sections in accordance with the patrol schedule, identify and address defects and, depending on the degree of danger, report in good time problems they cannot resolve themselves.

Railway transport organs shall draw up railway line monitoring plans based on the directives of the relevant higher-level organ and meteorological observations, send the plans to the units that will conduct the monitoring, and regularly ascertain the status of monitoring and take appropriate measures.

Article 37 (Methods of monitoring and reports on railway line monitoring)

Section titled “Article 37 (Methods of monitoring and reports on railway line monitoring)”

Railway lines shall be monitored by fixed and temporary monitoring.

Railway monitoring personnel shall responsibly monitor railway lines and structures in their assigned sections and report the status of monitoring in good time at the prescribed times.

Article 38 (Establishment of railway line protection zones)

Section titled “Article 38 (Establishment of railway line protection zones)”

A specified area extending from a railway line shall be designated as a railway line protection zone to protect the railway line.

The railway line protection zone shall extend 2 m from the foot of the track bed, or from the top of the required slope in a cutting, and 3 m in wetlands.

Land within the railway line protection zone shall be managed by the railway transport organ. Registered agricultural land shall be managed by the relevant land user institution.

Article 39 (Prohibitions in railway line protection zones)

Section titled “Article 39 (Prohibitions in railway line protection zones)”

No person may, in a railway line protection zone:

  1. Graze domestic animals
  2. Make water channels other than railway drainage ditches or lay paths
  3. Cut trees or remove ground cover plants such as grass
  4. Dig up or remove soil or gravel
  5. Use explosives or light fires
  6. Violate the rules on passage along railway lines or across railway crossings
  7. Sit on a railway line or sleep on a railway line or in a railway line protection zone
  8. Otherwise hinder protection of a railway line

Article 40 (Management of the surroundings of railway lines)

Section titled “Article 40 (Management of the surroundings of railway lines)”

Railway transport organs, local people’s committees and the relevant institutions, enterprises and organizations shall plant flowering shrubs on the track bed and bush clover and ground cover plants on the slopes, and transplant in good time trees that interfere with train operation or railway communication lines.

Track beds and slopes shall be managed by the responsible railway transport organs, institutions, enterprises and organizations. Land and planted trees outside railway line protection zones shall be managed by forestry management organs, city management organs and the relevant institutions.

Article 41 (Works to protect railway lines and structures)

Section titled “Article 41 (Works to protect railway lines and structures)”

Railway transport organs, local people’s committees and the relevant institutions, enterprises and organizations shall build retaining walls, landslide barriers and drainage works where necessary, including on railway embankments and on riverbanks and mountain slopes near railway bridges and tunnels, to protect railway lines and structures from damage caused by natural events.

Local people’s committees and the relevant institutions, enterprises and organizations shall observe the rules on managing and using rivers and streams flowing under railway bridges so that the bridges do not suffer flood damage.

Article 42 (Installation and responsibility for management of railway line safety facilities)

Section titled “Article 42 (Installation and responsibility for management of railway line safety facilities)”

Safety facilities for railway line protection shall be installed and managed as follows:

  1. Railway transport organs and the relevant institutions shall install and manage safety facilities on railway bridges as prescribed.
  2. Road management organs shall install and manage safety facilities, including railway bridge clearance barriers, on roads passing under railway bridges.
  3. Institutions, enterprises and organizations that manage or use power transmission, power distribution or communications lines shall install and manage safety nets below any such lines passing over railway lines.
  4. Institutions, enterprises and organizations that manage level crossings shall build monitoring posts and install and manage safety facilities of all kinds, including barriers and automatic warning devices.
  5. Railway transport organs shall remove cracked rock from slopes beside the track bed or take the necessary safety measures to prevent rockfalls.

When carrying out railway line repair or management work, railway transport organs, local people’s committees and the relevant institutions, enterprises and organizations shall post lookouts in both directions from the work area and take the necessary labour safety measures to prevent accidents thoroughly.

Article 44 (Scientification of railway line protection)

Section titled “Article 44 (Scientification of railway line protection)”

Railway transport organs shall establish a scientific system of technical management for railway line protection, use modern railway line inspection and measuring means to improve preventive repair, protection and management of railway lines and structures, and maintain their technical condition at a high standard.

Article 45 (Provision of conditions for the railway line sector)

Section titled “Article 45 (Provision of conditions for the railway line sector)”

State planning organs, labour administration organs, financial organs, commercial organs, light industry organs, public health organs, local people’s committees and the relevant institutions shall take responsibility for providing the workers, materials, funds, staple food, basic foodstuffs and daily necessities needed to build and protect railway lines.

Employees in the railway line management sector, including patrol workers and monitoring personnel, may not be mobilized for work unrelated to the railway line sector.

Article 46 (Building up of a railway fund)

Section titled “Article 46 (Building up of a railway fund)”

A railway fund shall be built up and used to strengthen and maintain the stability of the material and technical foundation of the railway, including the construction, protection and management of railway lines.

The railway fund may not be used for work unrelated to the railway sector.

Article 47 (Rolling stock eligible to use railway lines)

Section titled “Article 47 (Rolling stock eligible to use railway lines)”

Only rolling stock approved by the railway transport organ may operate on railway lines.

Rolling stock shall be operated under unitary dispatch command.

Article 48 (Approval to use railway lines)

Section titled “Article 48 (Approval to use railway lines)”

Approval to use a railway line shall be granted to a unit that has paid the railway transport charge.

Payment of the railway transport charge shall be confirmed by a certificate of payment issued by the central railway transport guidance organ.

Article 49 (Prevention of damage to railway lines)

Section titled “Article 49 (Prevention of damage to railway lines)”

Institutions, enterprises and organizations using railway lines shall make thorough preparations for freight transport so that railway lines and their protection zones are not damaged or destroyed in the course of transport.

Article 50 (Construction of railway crossings)

Section titled “Article 50 (Construction of railway crossings)”

As a rule, railway crossings shall be built as overpasses or underpasses with at least 2 km between crossings. Where an overpass or underpass cannot be built, a level crossing shall be constructed.

Approval from the central railway transport guidance organ shall be obtained before a railway crossing is built or removed.

Article 51 (Installation of railway crossing monitoring posts)

Section titled “Article 51 (Installation of railway crossing monitoring posts)”

Institutions, enterprises and organizations managing level crossings shall install monitoring posts and safety facilities and assign permanent monitoring personnel to ensure safe passage by trains, automobiles and other wheeled vehicles, and people.

Institutions, enterprises and organizations intending to establish a temporary level crossing as necessary shall obtain the agreement of the local public security organ and road management organ and the approval of the railway transport organ. They shall then establish the crossing, install monitoring posts and safety facilities in accordance with the standards and assign monitoring personnel.

A level crossing approved on a temporary basis shall be removed as soon as its authorized period of use ends. The railway transport organ, public security organ and road management organ for the relevant area shall then be informed.

Article 52 (Railway line signs and markers)

Section titled “Article 52 (Railway line signs and markers)”

Railway transport organs, local people’s committees and the relevant institutions, enterprises and organizations shall install railway line signs and markers, such as line signs, signals, advance warning signs and distance markers, at designated places to facilitate use of railway lines.

Railway line signs and markers shall be made to standards approved by the central railway transport guidance organ and installed at the prescribed places.

Article 53 (Prohibition on travelling along railway lines)

Section titled “Article 53 (Prohibition on travelling along railway lines)”

Residents may not travel on railway lines or enter railway lines within station grounds without approval from the railway transport organ. They may not drive means of transport, including automobiles, tractors and ox- or horse-drawn carts, across railway lines except at railway crossings.

Article 54 (Prohibition on construction that interferes with railway line use)

Section titled “Article 54 (Prohibition on construction that interferes with railway line use)”

Institutions, enterprises, organizations and citizens shall not carry out construction that interferes with the use of railway lines, such as installing temporary buildings, warehouses or facilities.

Where construction is necessary, the agreement of the relevant railway safety organ and the approval of the railway transport organ shall be obtained. Railway safety facilities shall be provided so that train operation is not disrupted.

Article 55 (Penalties of restoration and restitution)

Section titled “Article 55 (Penalties of restoration and restitution)”

In the following cases, the person responsible shall be required to restore the original condition or make restitution:

  1. Where a railway line has been harmed or damaged by failure to manage the assigned section in accordance with technical regulations
  2. Where railway facilities such as a railway bridge, overhead contact line, communications line pole or railway crossing barrier have been damaged because a wheeled vehicle operating within station grounds or on a road exceeded the permitted load height, was driven carelessly or broke down
  3. Where the track bed or structures have suffered flood damage through disorderly use or improper management of a river or stream flowing under a railway bridge

Where an accident due to a defect in a railway line causes damage, compensation shall be provided for the damage.

Compensation shall be governed by the Law on Compensation for Damage.

In the following cases, institutions, enterprises and organizations shall be fined 100,000 to 1,500,000 won and individual citizens shall be fined 1,000 to 100,000 won:

  1. Where repair or management has not been organized in accordance with the railway line repair plan or the person or body concerned has failed to take part in mobilized damage recovery work
  2. Where a risk of accident has been created during railway line repair, cleaning, snow clearance or similar work by failure to install barriers or slow-running signs or to post lookouts
  3. Where there is no certificate of payment of railway transport charges, a risk of accident has been created by operating a defective vehicle, or the surroundings of a railway line have been soiled and structures harmed or damaged
  4. Where a temporary crossing has been established or used without approval from the railway transport organ, has not been removed immediately upon expiry of its period of use, or the railway line and protection zone have not been restored to their original condition after removal
  5. Where automobiles, tractors, ox- or horse-drawn carts or self-made wheeled vehicles have been driven across railway lines somewhere other than a railway crossing
  6. Where a subsidiary plot has been cultivated or domestic animals have been grazed in a railway line protection zone
  7. Where a person travels along a railway line or sits on it
  8. Where monitoring personnel or patrol workers have left their posts or slept during duty hours or have not properly performed their duties

Construction or use of a railway line shall be suspended in the following cases:

  1. Where a railway line is constructed without approval or the requirements of the construction design are not followed
  2. Where there is no certificate of payment of railway transport charges or defective rolling stock capable of damaging a railway line is operated
  3. Where a railway line has been destroyed by a natural disaster or accident, or its condition is poor enough to cause a train accident

Railway track fastenings collected unlawfully and wheeled vehicles made and used without approval shall be confiscated.

Article 60 (Penalties of warning and stern warning)

Section titled “Article 60 (Penalties of warning and stern warning)”

In the following cases, the person responsible shall be given the penalty of warning:

  1. Where railway line structures have not been properly reinforced, works to protect railway facilities have not been properly carried out or safety facilities have not been properly installed or managed
  2. Where railway crossing posts have not been properly built, monitoring personnel have not been properly assigned or railway crossing safety facilities have not been properly installed or managed
  3. Where buildings or facilities unrelated to railway operations have been built or approved for construction in a railway line protection zone or within 1 to 2 km of a railway line
  4. Where rice paddies or fields have been cultivated or roads or water channels have been built within a railway line protection zone without approval from the central railway transport guidance organ
  5. Where railway line inspection, repair, monitoring or patrol has not been carried out properly
  6. Where scientific research or training of technicians or specialists in the railway line sector has been impeded

Where the circumstances of an act under the preceding paragraph are grave, the penalty of stern warning shall be given.

Article 61 (Penalties of unpaid labour and labour education)

Section titled “Article 61 (Penalties of unpaid labour and labour education)”

In the following cases, the person responsible shall be given the penalty of unpaid labour or labour education of not more than three months:

  1. Where a railway line that has not undergone completion inspection has been operated
  2. Where retaining wall, landslide protection or drainage works at hazardous sections of a railway line have not been carried out or have been carried out irresponsibly
  3. Where a railway line has been constructed or a new railway crossing established without approval from the central railway transport guidance organ, or a temporary railway crossing has not been removed when its period of use expired
  4. Where concrete sleepers, fastenings or rails of unverified quality have been used
  5. Where railway line construction has not followed the requirements of construction methods
  6. Where production of concrete sleepers or railway track fastenings or construction, protection or management of railway lines has been impeded by failure to provide construction materials and equipment needed for that work, including steel materials, cement and wheeled vehicles
  7. Where construction, protection or management of railway lines has been impeded by failure to provide the workers needed in the railway line sector in good time or by mobilizing workers in the railway line sector for other work
  8. Where an accident causing casualties has resulted from failure to properly conduct education on protecting and using railway lines
  9. Where a person has travelled on or sat on a railway bridge or in a tunnel, or slept on a railway line
  10. Where railway ballast has been dug up
  11. Where a wheeled vehicle has been operated without approval or a self-made wheeled vehicle has been operated
  12. Where not more than 1 kg of railway track fastenings has been illicitly traded or collected

Where the circumstances of an act under the preceding paragraph are grave, the penalty of unpaid labour or labour education of not less than three months shall be given.

Article 62 (Penalties of demotion, dismissal and removal from post)

Section titled “Article 62 (Penalties of demotion, dismissal and removal from post)”

Where a failure to properly carry out State policy in the railway line management sector has caused serious consequences, the penalty of demotion, dismissal or removal from post shall be given according to the gravity of the conduct.

Where an act in violation of this Law amounts to a crime, criminal liability shall be imposed on the person responsible in accordance with the relevant article of the Criminal Law.

The Law of the Democratic People’s Republic of Korea on the Management of Railway Lines, as amended and supplemented by Decree No. 1530 of the Standing Committee of the Supreme People’s Assembly of 17 January Juche 113 (2024), shall enter into force on 1 February Juche 113 (2024).

English translations by NK Law are licensed under CC BY-SA 4.0.Copyright and reuse

Contact info@nklaw.org

Privacy policy