Underground Resources Law of the Democratic People's Republic of Korea
Edition dated 26 October 2021. August 2024 NIS compilation, vol. 1, pp. 960–970
Adopted on 8 April Juche 82 (1993) by Ordinance No. 14 of the Supreme People’s Assembly
Amended and supplemented on 26 February Juche 88 (1999) by Decree No. 483 of the Standing Committee of the Supreme People’s Assembly
Amended and supplemented on 28 December Juche 93 (2004) by Decree No. 868 of the Standing Committee of the Supreme People’s Assembly
Amended and supplemented on 8 August Juche 95 (2006) by Decree No. 1901 of the Standing Committee of the Supreme People’s Assembly
Amended and supplemented on 8 May Juche 96 (2007) by Decree No. 2227 of the Standing Committee of the Supreme People’s Assembly
Amended and supplemented on 28 July Juche 98 (2009) by Decree No. 197 of the Standing Committee of the Supreme People’s Assembly
Amended and supplemented on 21 February Juche 102 (2013) by Decree No. 2979 of the Standing Committee of the Supreme People’s Assembly
Amended and supplemented on 23 November Juche 105 (2016) by Decree No. 1421 of the Standing Committee of the Supreme People’s Assembly
Amended and supplemented on 20 April Juche 106 (2017) by Decree No. 1688 of the Standing Committee of the Supreme People’s Assembly
Amended and supplemented on 8 October Juche 109 (2020) by Decree No. 439 of the Standing Committee of the Supreme People’s Assembly
Amended and supplemented on 26 October Juche 110 (2021) by Decree No. 757 of the Standing Committee of the Supreme People’s Assembly
Source · Republic of Korea National Intelligence Service, Compilation of North Korean Laws (북한법령집), August 2024, vol. 1, pp. 960–970.
The first draft of this translation was produced with AI assistance.
Chapter 1. Fundamentals of the Underground Resources Law
Section titled “Chapter 1. Fundamentals of the Underground Resources Law”Article 1 (Mission of the Underground Resources Law)
Section titled “Article 1 (Mission of the Underground Resources Law)”The Underground Resources Law of the Democratic People’s Republic of Korea contributes to speeding up socialist economic construction and raising the people’s living standards by establishing discipline and order in the exploration, development and use of underground resources.
Article 2 (Classification and ownership of underground resources)
Section titled “Article 2 (Classification and ownership of underground resources)”Underground resources include mineral resources such as metals, non-metals, combustible minerals and tailings, and groundwater resources such as geothermal resources, hot springs, medicinal springs, springs, geothermal water and underground brine.
In the Democratic People’s Republic of Korea, underground resources are owned by the State alone.
Article 3 (Principle of underground resources exploration)
Section titled “Article 3 (Principle of underground resources exploration)”Underground resources exploration is the scouting front of building an economic power.
The State shall ensure that underground resources are found in greater quantities and more quickly, by attaching importance to underground resources exploration work and firmly putting it first, decisively strengthening exploration forces, and achieving the Juche orientation, modernization, informatization and scientification of exploration.
Article 4 (Principle of underground resources development)
Section titled “Article 4 (Principle of underground resources development)”Vigorously carrying out underground resources development work is an essential requirement for strengthening the foundation of the independent national economy and improving the people’s living standards.
The State shall concentrate investment in the underground resources development sector and ensure that underground resources development is carried out with a long-term view under the unified guidance of the State.
Article 5 (Principle of effective and rational use of underground resources)
Section titled “Article 5 (Principle of effective and rational use of underground resources)”Underground resources are precious wealth for the prosperity of the country and the happiness of the people.
The State shall ensure that underground resources are used effectively and rationally, by establishing rules on the use of underground resources and strengthening scientific research work.
Article 6 (Principle of mass-based protection of underground resources)
Section titled “Article 6 (Principle of mass-based protection of underground resources)”Actively protecting underground resources is a sacred duty of institutions, enterprises, organizations and citizens.
The State shall ensure that the entire people participate as masters in underground resources protection work, by strengthening education in patriotism.
Article 7 (Principle of guidance and control of the underground resources sector)
Section titled “Article 7 (Principle of guidance and control of the underground resources sector)”The State shall establish an orderly work system in the underground resources exploration, development and use sector and strengthen guidance and control of this sector.
Article 8 (Exchange and cooperation in the underground resources field)
Section titled “Article 8 (Exchange and cooperation in the underground resources field)”The State shall develop exchange and cooperation with various countries of the world in the field of underground resources exploration, development and use.
Chapter 2. Underground resources exploration
Section titled “Chapter 2. Underground resources exploration”Article 9 (Basic requirement for underground resources exploration)
Section titled “Article 9 (Basic requirement for underground resources exploration)”Putting underground resources exploration first is an important undertaking for economic development and provision for the people’s livelihood.
Underground resources exploration institutions and enterprises shall carry out underground resources exploration first, according to plan, so as to fully ensure the supply of the fuel and raw materials needed by various sectors of the national economy and to contribute to the living and health promotion of the people.
Article 10 (Drawing up of the underground resources exploration plan)
Section titled “Article 10 (Drawing up of the underground resources exploration plan)”The State planning organ shall draw up the underground resources exploration plan on the basis of the national economic demand for underground resources and the geological conditions.
Where the geological conditions are newly clarified, the underground resources exploration plan shall be revised accordingly.
Article 11 (Classification of exploration)
Section titled “Article 11 (Classification of exploration)”Underground resources exploration is divided into prospective exploration, current exploration and operational exploration.
Underground resources exploration institutions and enterprises shall make clear the duties and limits of responsibility corresponding to prospective exploration, current exploration and operational exploration, and strictly observe them.
Article 12 (Prospective exploration)
Section titled “Article 12 (Prospective exploration)”Prospective exploration shall be carried out mainly by exploration institutions and enterprises belonging to the central underground resources development guidance organ, but where necessary, exploration institutions and enterprises belonging to underground resources development units may also carry it out. In this case, the approval of the central underground resources development guidance organ shall be obtained.
In prospective exploration, the distribution of underground resources shall be revealed three-dimensionally and scientifically, going ahead by 10 to 20 years or more, and a greater number of promising coal and mineral deposits shall be found.
The central underground resources development guidance organ shall properly determine prospective exploration areas on the basis of scientific interpretation of geological survey data, and shall ensure that, with drilling exploration as the main method, various kinds of exploration including tunnel exploration are rationally combined.
Article 13 (Current exploration)
Section titled “Article 13 (Current exploration)”Current exploration shall be carried out by exploration institutions and enterprises belonging to underground resources development units.
In current exploration, ample coal and mineral reserves that can be mined for not less than 10 years shall be secured in the deep parts and surrounding areas of coal mines and mines under operation or development.
Article 14 (Operational exploration)
Section titled “Article 14 (Operational exploration)”Operational exploration shall be carried out by underground resources development institutions, enterprises and organizations.
Underground resources development institutions, enterprises and organizations shall, centring on preparing the scientific and technical guarantee that can ensure rational mining in the anticipated mining areas, organize and carry out operational exploration not less than one year ahead.
Underground resources development institutions, enterprises and organizations shall carry out operational exploration according to plan and put main driveage ahead by not less than three years and preparatory driveage by not less than six months.
Article 15 (Exploration of geothermal and groundwater resources)
Section titled “Article 15 (Exploration of geothermal and groundwater resources)”Exploration of geothermal and groundwater resources shall be carried out by underground resources exploration institutions and enterprises with the approval of the central underground resources development guidance organ.
Article 16 (Observance of exploration stages)
Section titled “Article 16 (Observance of exploration stages)”Underground resources exploration institutions and enterprises shall duly observe the exploration stages and raise exploration efficiency and the effectiveness of investment.
In underground resources exploration, scientific geological survey work shall be put first, the target areas to be explored shall be accurately defined, preliminary exploration shall be conducted to confirm underground resources with development prospects, and then detailed exploration shall be conducted to determine the reserves.
Article 17 (Underground resources exploration design)
Section titled “Article 17 (Underground resources exploration design)”The underground resources exploration design shall be prepared by underground resources exploration institutions and enterprises.
Underground resources exploration institutions and enterprises shall, so as to eliminate futile exploration and repeated exploration and to find underground resources without omission, prepare a design for each exploration stage and submit it to the central underground resources development guidance organ or the relevant institution, as the case may be.
The central underground resources development guidance organ and the relevant institution shall deliberate on the exploration design and approve or reject it within 10 days from the date of receipt. In this case, the approved exploration design shall be dovetailed with the plan.
Article 18 (Exploration of underground resources according to design)
Section titled “Article 18 (Exploration of underground resources according to design)”Underground resources exploration institutions and enterprises shall carry out exploration according to the approved design.
When mineral resources exploration is completed, drill holes, geological trenches and exploration wells shall be filled so as not to hinder mining work and land use, and when geothermal and groundwater resources exploration is completed, drill holes and exploration wells shall be preserved so that they can be used.
Article 19 (Raising of exploration speed and efficiency, and organization of detailed exploration)
Section titled “Article 19 (Raising of exploration speed and efficiency, and organization of detailed exploration)”Underground resources exploration institutions and enterprises shall improve exploration methods, raise exploration speed and efficiency, and actively explore underground resources that are scarce in our country or have not yet been found.
Where the question of prospective exploration of an area for which development approval has already been obtained arises, development units may be moved out and detailed exploration may be organized with the approval of the Non-standing Resources Development Deliberation Committee.
Article 20 (Standards for calculating underground resources reserves)
Section titled “Article 20 (Standards for calculating underground resources reserves)”The standards for calculating underground resources reserves shall be fixed by the Non-standing Resources Development Deliberation Committee.
The Non-standing Resources Development Deliberation Committee shall renew the standards for calculating underground resources reserves as the underground resources reserves change or science and technology develop.
Article 21 (Calculation of and deliberation on underground resources reserves)
Section titled “Article 21 (Calculation of and deliberation on underground resources reserves)”Underground resources exploration institutions and enterprises shall accurately calculate underground resources reserves on the basis of exploration data and the standards for calculating underground resources reserves.
The calculated underground resources reserves shall be deliberated on and approved by the central underground resources development guidance organ and the relevant institution.
Article 22 (Registration of underground resources reserves)
Section titled “Article 22 (Registration of underground resources reserves)”Approved underground resources reserves shall be registered with the central underground resources development guidance organ and the relevant exploration institution or enterprise.
Underground resources reserves not registered with the central underground resources development guidance organ may not be an object of development design.
Article 23 (Stocktaking of underground resources reserves and registration of changes)
Section titled “Article 23 (Stocktaking of underground resources reserves and registration of changes)”The central underground resources development guidance organ and underground resources exploration and development institutions, enterprises and organizations shall carry out stocktaking of underground resources reserves periodically and accurately keep track of and register changes in underground resources reserves.
Registered underground resources reserves may not be reduced without the approval of the central underground resources development guidance organ.
Chapter 3. Underground resources development
Section titled “Chapter 3. Underground resources development”Article 24 (Basic requirement for underground resources development)
Section titled “Article 24 (Basic requirement for underground resources development)”Underground resources development is an important condition for normalizing production in various sectors of the national economy and improving the people’s living standards.
Mineral resources development institutions, enterprises and organizations shall increase mineral production by making extraction equipment large-scale, modern and high-speed, diversifying transport, putting driveage first and adopting efficient mining methods, while geothermal and groundwater resources development institutions, enterprises and organizations shall develop geothermal and groundwater resources effectively on the basis of thoroughly ensuring the safety of buildings and structures in residential areas.
Article 25 (Underground resources development deliberation organ and objects of deliberation)
Section titled “Article 25 (Underground resources development deliberation organ and objects of deliberation)”Underground resources may be developed only after obtaining the approval of the underground resources development deliberation organ. However, groundwater resources to be used for agricultural production or residents’ living in rural and mountainous areas and the like, or groundwater resources of little economic use value because of small yield, may be used by registering with the relevant institution, without obtaining underground resources development approval.
Deliberation on the development of mineral resources shall be conducted by the Non-standing Resources Development Deliberation Committee, and deliberation on the development of geothermal and groundwater resources shall be conducted by the Non-standing Resources Development Deliberation Committee or the relevant institution, depending on the scale, value and importance of the development project.
Article 26 (Examination of the written application for underground resources development approval)
Section titled “Article 26 (Examination of the written application for underground resources development approval)”An institution, enterprise or organization that intends to obtain underground resources development approval shall prepare a written application for underground resources development approval and submit it to the central underground resources development guidance organ.
The central underground resources development guidance organ shall, within 20 days from the date of receipt of the written application for underground resources development approval, examine the purpose and scale of the underground resources development, the reserves, the grade, the water quality analysis data and the like.
Article 27 (Deliberation on and handling of applications for underground resources development approval)
Section titled “Article 27 (Deliberation on and handling of applications for underground resources development approval)”The central underground resources development guidance organ shall, after obtaining the agreement of the relevant institution on the written application for underground resources development approval, submit it to the deliberation of the underground resources development deliberation organ.
The underground resources development deliberation organ shall conduct deliberation on underground resources development in accordance with the long-term plan and measures for the unified and rational use of underground resources, and approve or reject it.
Where underground resources development is approved, an underground resources development approval certificate stating the name of the development unit, the development area, the period of validity of development and the like shall be issued. In this case, the period of validity of development in the underground resources development approval certificate shall be fixed according to the mining term, and for coal mines and mines for which it is difficult to determine the mining term, it shall be fixed as a separately prescribed period.
The period of validity of development in the underground resources development approval certificate may be extended in accordance with the procedure laid down by the Cabinet.
An institution, enterprise or organization that has been issued an underground resources development approval certificate shall pay the prescribed underground resources development right price and fees.
Article 28 (Land use permit and site designation)
Section titled “Article 28 (Land use permit and site designation)”The land and environment protection organ and the agricultural guidance organ shall provide the forest land and agricultural land specified in the underground resources development approval certificate in accordance with the rules on land use permits and shall carry out site designation for it.
A land use permit and site designation may not be given to an institution, enterprise or organization that has not obtained underground resources development approval.
Article 29 (Preparation and approval of the underground resources development technical assignment and technical design)
Section titled “Article 29 (Preparation and approval of the underground resources development technical assignment and technical design)”The underground resources development technical assignment and technical design shall be prepared by the relevant design institution and underground resources development institutions, enterprises and organizations.
The relevant design institution and underground resources development institutions, enterprises and organizations shall prepare the underground resources development technical assignment and technical design so as to achieve a high extraction rate and production efficiency.
The prepared underground resources development technical assignment shall be deliberated on and approved by the State planning organ, and the technical design by the central design guidance organ or the relevant institution.
Article 30 (Underground resources development according to design)
Section titled “Article 30 (Underground resources development according to design)”Underground resources development shall be carried out in accordance with the underground resources development design.
Underground resources development institutions, enterprises and organizations shall observe the requirements of the underground resources development design and raise the effectiveness of investment.
Article 31 (Underground resources development technical indicator plan)
Section titled “Article 31 (Underground resources development technical indicator plan)”The underground resources development technical indicator plan shall be drawn up by underground resources development institutions, enterprises and organizations and the relevant institution.
Underground resources development institutions, enterprises and organizations and the relevant institution shall properly draw up underground resources development technical indicator plans such as extraction rate plans and ore dressing recovery rate plans.
Article 32 (Rational organization of mining)
Section titled “Article 32 (Rational organization of mining)”Underground resources development institutions, enterprises and organizations shall organize mining rationally and mine the whole of the ore bodies that meet the mining standard and the standard for calculating underground resources reserves.
They may not select and mine only ore bodies with good mining conditions, or of high grade and thickness.
Article 33 (Registration of underground resources that cannot be mined)
Section titled “Article 33 (Registration of underground resources that cannot be mined)”Underground resources development institutions, enterprises and organizations shall keep track of and register underground resources that cannot be mined at present because they do not meet the mining standard or because mining conditions are not in place, and underground resources remaining in stopes, and shall mine them as the mining conditions are met.
Article 34 (Closure of mines, closure of shafts and plugging of boreholes)
Section titled “Article 34 (Closure of mines, closure of shafts and plugging of boreholes)”An institution, enterprise or organization developing mineral resources shall, where it intends to close a coal mine or mine or close a shaft, carry out the underground resources exploration and mining work that can be done using the shaft and record the state of the shaft and stope in detail, and an institution, enterprise or organization developing geothermal and groundwater resources shall, where it intends to plug a borehole, record the water level and water quality in detail.
A coal mine or mine may not be closed or a shaft closed, and a geothermal or groundwater borehole may not be plugged, without the approval of the underground resources development deliberation organ.
Article 35 (Prevention of accidents and damage from natural hazards)
Section titled “Article 35 (Prevention of accidents and damage from natural hazards)”Underground resources development institutions, enterprises and organizations shall thoroughly observe technical regulations and labour safety regulations in underground resources development and prevent accidents and damage from natural hazards.
Article 36 (Preservation of the living environment and ecological environment)
Section titled “Article 36 (Preservation of the living environment and ecological environment)”Institutions, enterprises, organizations and citizens developing underground resources shall not, in the course of underground resources development, destroy the living environment of residents, including land, resources and natural scenery, and the ecological environment of flora and fauna.
Article 37 (Agreement on construction in areas where underground resources development is anticipated)
Section titled “Article 37 (Agreement on construction in areas where underground resources development is anticipated)”An institution, enterprise or organization that intends to build roads, railways, factories, water sources and the like occupying wide sites in an area where underground resources development is anticipated shall obtain the agreement of the central underground resources development guidance organ.
Article 38 (Protection of unusual geological phenomena, rare minerals and fossils)
Section titled “Article 38 (Protection of unusual geological phenomena, rare minerals and fossils)”Institutions, enterprises, organizations and citizens that, in the course of underground resources exploration, mining, construction work and the like, discover new kinds of underground resources, unusual geological phenomena, rare minerals, fossils and the like shall take measures to protect them and inform the relevant institution.
Chapter 4. Use of underground resources
Section titled “Chapter 4. Use of underground resources”Article 39 (Raising the utilization rate of underground resources)
Section titled “Article 39 (Raising the utilization rate of underground resources)”Using underground resources effectively is an important means of meeting the growing demand of the national economy for raw materials and fuel.
The relevant institutions, enterprises and organizations shall actively protect underground resources and raise their utilization rate.
Individual citizens may not engage in acts such as illegally extracting underground resources or smelting or making iron.
Article 40 (Provision of conditions for the management of underground resources)
Section titled “Article 40 (Provision of conditions for the management of underground resources)”The relevant institutions, enterprises and organizations shall build up in a modern way and manage well loading and unloading facilities, coal yards, ore storage sheds and warehouses, so that mineral resources such as coal, ore, concentrate and crude oil are not wasted.
Geothermal and groundwater development institutions, enterprises and organizations shall regularly maintain and repair groundwater intake facilities such as borehole casing, pumps, transmission mains and waterways, and eliminate the loss of groundwater in transit.
Article 41 (Prevention of loss of underground resources in transit)
Section titled “Article 41 (Prevention of loss of underground resources in transit)”Railway transport organs and the relevant institutions, enterprises and organizations shall regularly maintain and reinforce means of transport and thoroughly organize transport so that mineral resources are not lost in transit.
Article 42 (Achieving the recovery rate standard in mineral resources processing)
Section titled “Article 42 (Achieving the recovery rate standard in mineral resources processing)”The relevant institutions, enterprises and organizations shall observe technical regulations and standard operating procedures in mineral resources processing processes such as ore dressing and smelting, and achieve the prescribed recovery rate standard.
Work that cannot achieve the prescribed recovery rate standard shall not be carried out.
Article 43 (Processing of mineral resources)
Section titled “Article 43 (Processing of mineral resources)”The relevant institutions, enterprises and organizations shall build up production technology processes for the comprehensive processing of mineral resources and recover their main components and secondary components.
Where valuable components in fine ore, waste rock, tailings and slag cannot be recovered, the fine ore, waste rock, tailings and slag shall be stored and not discarded.
Underground resources development institutions, enterprises and organizations may not process minerals illegally received from other units while not producing minerals.
Article 44 (Use of substitute mineral raw materials and fuel)
Section titled “Article 44 (Use of substitute mineral raw materials and fuel)”The relevant institutions, enterprises and organizations shall actively use mineral resources that are scarce in our country or have not yet been found as substitute mineral raw materials and fuel.
Article 45 (Export of underground resources)
Section titled “Article 45 (Export of underground resources)”The export of underground resources shall be restricted as far as possible.
Underground resources may be exported only by units approved by the Cabinet.
Underground resources export units shall, in accordance with the underground resources export quota received from the Non-standing Import and Export Deliberation Committee, receive an export plan from the State planning organ and export underground resources.
Article 46 (Effective use of mineral spring resources and prohibition of acts changing their component content)
Section titled “Article 46 (Effective use of mineral spring resources and prohibition of acts changing their component content)”Institutions and enterprises managing mineral spring resources shall build up the mineral spring protection zone in a hygienic and cultured way and effectively use medicinal springs, hot springs and the like.
Without the agreement of the mineral spring resources management institution, no person may explore mineral resources in the mineral spring protection zone or carry out development or construction work by such means as blasting, thereby causing mineral spring resources to decrease or changing their component content.
Article 47 (Use of underground resources for designated purposes)
Section titled “Article 47 (Use of underground resources for designated purposes)”Institutions, enterprises and organizations shall use underground resources only for the purposes fixed by the State.
Groundwater used to obtain geothermal heat shall be returned underground.
Chapter 5. Guidance and control of the exploration, development and use of underground resources
Section titled “Chapter 5. Guidance and control of the exploration, development and use of underground resources”Article 48 (Basic requirement for guidance of underground resources exploration, development and use)
Section titled “Article 48 (Basic requirement for guidance of underground resources exploration, development and use)”Guidance of underground resources exploration, development and use shall be exercised by the central underground resources development guidance organ and the relevant central organs under the unified guidance of the Cabinet.
The central underground resources development guidance organ and the relevant central organs shall strengthen guidance of underground resources exploration, development and use in line with the requirements of the development of the national economy.
Article 49 (Organ guiding underground resources protection and management work)
Section titled “Article 49 (Organ guiding underground resources protection and management work)”Guidance of underground resources protection and management work shall be exercised in a unified manner by the Non-standing Resources Development Deliberation Committee.
The Non-standing Resources Development Deliberation Committee shall establish an underground resources protection and management system and guide the relevant institutions, enterprises and organizations to actively protect and responsibly manage underground resources.
Article 50 (State support for the underground resources exploration and development sector)
Section titled “Article 50 (State support for the underground resources exploration and development sector)”The State shall establish a social ethos of actively helping the underground resources exploration and development sector and accord special preferential treatment to the working people of this sector.
Article 51 (Provision of conditions for underground resources exploration and development)
Section titled “Article 51 (Provision of conditions for underground resources exploration and development)”The State planning organ, the labour administration organ, the materials supply organ and the finance and banking organ shall give priority to ensuring the supply of the labour, equipment, materials and funds needed by the underground resources exploration and development sector.
The labour, equipment, materials and funds of the underground resources exploration and development sector may not be diverted to other uses.
Article 52 (Scientific research work and training of technicians and specialists for the underground resources exploration and development sector)
Section titled “Article 52 (Scientific research work and training of technicians and specialists for the underground resources exploration and development sector)”Scientific research institutions and education institutions shall strengthen scientific research work for putting the underground resources exploration, development and use sector on a new scientific and technical foundation, and bring up more capable technicians and specialists.
Article 53 (Supervision and control of underground resources exploration, development and use)
Section titled “Article 53 (Supervision and control of underground resources exploration, development and use)”Supervision and control of underground resources exploration, development and use shall be exercised by the underground resources protection supervision organ and the relevant supervision and control organ.
The underground resources protection supervision organ and the relevant supervision and control organ shall regularly supervise and control underground resources exploration, development and use.
The relevant land supervision organ shall strictly supervise and control acts of digging up land for the purpose of illegal mining of underground resources in the area under its jurisdiction.
Article 54 (Civil liability)
Section titled “Article 54 (Civil liability)”Civil liability such as restoration to the original state or compensation for damage shall be imposed on a party that, in violation of this Law, has caused damage to other institutions, enterprises, organizations and citizens.
Article 55 (Cancellation of underground resources development approval)
Section titled “Article 55 (Cancellation of underground resources development approval)”Underground resources development approval may be cancelled in the following cases:
- Where the application for underground resources development has been made falsely
- Where development has not been commenced within six months from the date underground resources development was approved, or development has been suspended for not less than six months after it was commenced
- Where the underground resources development right has been transferred to another institution, enterprise or organization without approval
Article 56 (Penalty of restitution)
Section titled “Article 56 (Penalty of restitution)”The penalty of restitution shall be given to institutions, enterprises, organizations and citizens that have caused damage to the State by violating the rules on the development and use of underground resources.
Article 57 (Penalty of a fine)
Section titled “Article 57 (Penalty of a fine)”In the following cases, the relevant institution, enterprise or organization shall be fined:
- Where underground resources have been developed without going through the relevant approval procedures: 500,000 to 1,500,000 won
- Where underground resources have been developed in violation of the requirements of the design: 300,000 to 1,500,000 won
- Where underground resources have been developed without observing technical regulations and labour safety conditions: 500,000 to 1,500,000 won
- Where the environment has been destroyed in the course of underground resources development: 200,000 to 1,500,000 won
- Where an underground resources development unit has processed minerals illegally received from another unit while not producing minerals: 200,000 to 1,500,000 won
Article 58 (Penalty of suspension)
Section titled “Article 58 (Penalty of suspension)”Where, despite the demand of the supervision and control organ to rectify the act under Article 57, the deficiency has not been rectified, the development and use of underground resources shall be suspended. Where the circumstances are grave, closure of business shall be ordered.
Article 59 (Penalty of confiscation)
Section titled “Article 59 (Penalty of confiscation)”Where underground resources have been illegally extracted or illicitly traded, or used not in conformity with the designated purpose, the equipment, minerals, funds and goods used in or obtained through the unlawful act shall be confiscated.
Article 60 (Penalties of warning, stern warning, unpaid labour, labour education, demotion, dismissal and removal from post)
Section titled “Article 60 (Penalties of warning, stern warning, unpaid labour, labour education, demotion, dismissal and removal from post)”In the following cases, the person responsible shall be given the penalty of warning or stern warning, or the penalty of unpaid labour or labour education of not more than three months:
- Where underground resources development has been impeded through failure to carry out exploration properly
- Where exploration has not been carried out in accordance with the approved exploration design
- Where registration or stocktaking of the calculated underground resources reserves has not been carried out properly
- Where the rules on application and deliberation relating to underground resources development approval have been violated
- Where underground resources have been developed without going through the relevant approval procedures, or the underground resources development right has been transferred to another institution, enterprise or organization without approval
- Where underground resources have been developed without an underground resources development design, or in violation of the requirements of the design
- Where only ore bodies with good mining conditions, or of high grade and thickness, have been selected and mined
- Where the rules on closure of mines, closure of shafts and plugging of boreholes have been violated
- Where an accident has been caused by failure to observe technical regulations, standard operating procedures and labour safety conditions
- Where the environment has been destroyed in the course of underground resources development
- Where an individual has illegally extracted or illicitly traded underground resources, or has engaged in smelting or iron-making
- Where loading and unloading facilities, coal yards, ore storage sheds, warehouses or the like have not been properly provided and managed, or mineral resources have been lost through failure to organize and command mineral transport properly
- Where groundwater intake facilities have not been regularly maintained and repaired, causing the loss of groundwater in transit
- Where work has been continued although the recovery rate standard has not been achieved in mineral resources processing
- Where an underground resources development unit has processed minerals illegally received from another unit while not producing minerals
- Where measures for the storage of fine ore, waste rock, tailings or slag have not been properly taken
- Where the labour, equipment, materials or funds needed by the underground resources exploration and development sector have not been properly supplied, or the labour, equipment, materials and funds of this sector have been recklessly used for other work
Where the circumstances of an act under items 1 to 17 of the preceding paragraph are grave, the penalty of unpaid labour or labour education of not less than three months, or the penalty of demotion, dismissal or removal from post shall be given.
Article 61 (Criminal liability)
Section titled “Article 61 (Criminal liability)”Where an act in violation of this Law amounts to a crime, criminal liability shall be imposed on the person responsible in accordance with the relevant article of the Criminal Law.
English translations by NK Law are licensed under CC BY-SA 4.0.Copyright and reuse
Contact info@nklaw.org