Law of the Democratic People's Republic of Korea on Small and Medium-Sized Power Stations

Edition dated 25 October 2022. Korean source

Adopted on 11 April Juche 96 (2007) by Decree No. 2206 of the Standing Committee of the Supreme People’s Assembly
Amended and supplemented on 23 November Juche 105 (2016) by Decree No. 1421 of the Standing Committee of the Supreme People’s Assembly
Amended and supplemented on 25 October Juche 111 (2022) by Decree No. 1092 of the Standing Committee of the Supreme People’s Assembly

Korean source · NK TechLab Korean PDF, archived copy. The text comes from unchecked OCR of screenshots from a North Korean law app. Publisher’s source description

The OCR garbles the capacity unit in Article 2. The translations read the threshold as 20,000 kW, matching the earlier edition.

The first draft of this translation was produced with AI assistance.

Earlier edition

Chapter 1. Fundamentals of the Law on Small and Medium-Sized Power Stations

Section titled “Chapter 1. Fundamentals of the Law on Small and Medium-Sized Power Stations”

Article 1 (Mission of the Law on Small and Medium-Sized Power Stations)

Section titled “Article 1 (Mission of the Law on Small and Medium-Sized Power Stations)”

The Law of the Democratic People’s Republic of Korea on Small and Medium-Sized Power Stations, by strictly establishing the system and order in the construction and operation of small and medium-sized power stations and in the use of power, contributes to fully meeting the growing demand for power.

Article 2 (Definition of small and medium-sized power stations)

Section titled “Article 2 (Definition of small and medium-sized power stations)”

Small and medium-sized power stations are power stations with a generating capacity of up to 20,000 kW.

Small and medium-sized power stations include power stations that rely on various energy resources such as hydropower, thermal power, tidal power, solar power, wind power and biomass.

Article 3 (Principle of construction of small and medium-sized power stations)

Section titled “Article 3 (Principle of construction of small and medium-sized power stations)”

Speeding up the construction of small and medium-sized power stations is an essential requirement for increasing the country’s power generation.

The State shall ensure that investment in the construction of small and medium-sized power stations is systematically increased and internal sources are actively mobilized and used, so that a movement involving all the masses builds small and medium-sized power stations using various energy resources in keeping with local characteristics and economic benefit, with the construction of small and medium-sized hydropower stations as the basis.

Article 4 (Principle of operation of small and medium-sized power stations)

Section titled “Article 4 (Principle of operation of small and medium-sized power stations)”

The operation of small and medium-sized power stations is an important undertaking that generates electricity by maintaining the operating rate of generating equipment.

The State shall ensure that the integrated power management system for small and medium-sized power stations is properly established, equipment and technical management are improved, and their operation is normalized.

Article 5 (Principle of use of power from small and medium-sized power stations)

Section titled “Article 5 (Principle of use of power from small and medium-sized power stations)”

Using the power of small and medium-sized power stations properly is one of the basic ways to eliminate power loss and waste.

The State shall ensure that the power generated at small and medium-sized power stations is used effectively in keeping with their own circumstances.

Article 6 (Principle of introduction of scientific research results)

Section titled “Article 6 (Principle of introduction of scientific research results)”

The State shall strengthen scientific research work for raising the power generation and use efficiency of small and medium-sized power stations, and shall ensure that its results are actively adopted in the operation of small and medium-sized power stations.

Article 7 (Principle of saving electricity and protecting power facilities)

Section titled “Article 7 (Principle of saving electricity and protecting power facilities)”

The State shall strengthen education in patriotism among the people so that they save the electricity generated and actively protect the power facilities of small and medium-sized power stations.

Article 8 (Scope of application of the Law)

Section titled “Article 8 (Scope of application of the Law)”

This Law applies to institutions, enterprises, organizations and individual citizens that construct or operate small and medium-sized power stations, or use power generated at those stations.

Matters that are not prescribed in this Law shall be governed by the relevant laws and regulations.

Chapter 2. Construction of small and medium-sized power stations

Section titled “Chapter 2. Construction of small and medium-sized power stations”

Article 9 (Basic requirements for the construction of small and medium-sized power stations)

Section titled “Article 9 (Basic requirements for the construction of small and medium-sized power stations)”

Construction of small and medium-sized power stations is undertaken to mobilize and use the country’s power resources effectively.

Before building small and medium-sized power stations, the central electric power industry guidance organ, the small and medium-sized power station guidance organs and the relevant institutions, enterprises and organizations shall survey energy resources in detail. On that basis, they shall properly select construction sites, prepare designs on a scientific basis, set annual construction targets and carry out construction according to plan, beginning with projects of high economic effectiveness.

Article 10 (Drawing up of the construction plan)

Section titled “Article 10 (Drawing up of the construction plan)”

The construction plan for small and medium-sized power stations shall be drawn up by the State planning organ.

The State planning organ shall draw up the construction plan for small and medium-sized power stations, taking into account the demand for power, conditions of labour force, materials and equipment, and the like.

Article 11 (Submission and review of technical assignments)

Section titled “Article 11 (Submission and review of technical assignments)”

Institutions, enterprises and organizations that intend to build small and medium-sized power stations shall draw up technical assignments and submit them to the central planning guidance organ or the central electric power industry guidance organ according to the scale of the project.

The central planning guidance organ and the central electric power industry guidance organ shall review and handle technical assignments within 30 days.

Article 12 (Preparation of construction designs)

Section titled “Article 12 (Preparation of construction designs)”

Construction designs for small and medium-sized power stations shall be prepared by the power design institution or the relevant design institutions and enterprises.

The power design institution and the relevant design institutions and enterprises shall carry out surveying, geological investigation, site selection and the like accurately, assess economic effectiveness in accordance with the approved technical assignment and prepare a rational design proposal.

Article 13 (Deliberation and approval of construction designs)

Section titled “Article 13 (Deliberation and approval of construction designs)”

The relevant design guidance organ shall deliberate on and approve construction designs for small and medium-sized power stations.

The power design institution and the relevant design institutions and enterprises shall, according to the scale of the project, obtain the agreement of the small and medium-sized power station guidance organ or the central electric power industry guidance organ and submit their design proposal to the relevant design guidance organ.

Article 14 (Dovetailing the construction plan)

Section titled “Article 14 (Dovetailing the construction plan)”

The State planning organ shall closely dovetail the construction plan for small and medium-sized power stations for the construction client and for the construction contractor institutions, enterprises and organizations.

A project that is not dovetailed with the construction plan may not be constructed.

The construction client and contractor institutions, enterprises and organizations shall conclude a construction contract in accordance with the construction plan for small and medium-sized power stations.

A concluded construction contract shall be performed without fail.

Article 16 (Inspection by construction process)

Section titled “Article 16 (Inspection by construction process)”

The construction client and contractor institutions, enterprises and organizations shall appoint inspectors and strictly carry out quality inspection of construction.

Where the quality inspection is not passed, the work of the next process may not be continued.

Article 17 (Meeting the date for putting a station into operation)

Section titled “Article 17 (Meeting the date for putting a station into operation)”

Institutions, enterprises and organizations undertaking construction shall build small and medium-sized power stations in accordance with the requirements of the design and standard construction methods, and shall meet the date for putting them into operation.

Small and medium-sized power stations may not be constructed using an unapproved design, and the design may not be altered.

Article 18 (Construction of economically beneficial small and medium-sized hydropower stations)

Section titled “Article 18 (Construction of economically beneficial small and medium-sized hydropower stations)”

The relevant institutions, enterprises and organizations shall first build small and medium-sized hydropower stations of high economic benefit. In this case, they shall accurately survey hydropower resources and properly select hydropower sites.

Article 19 (Construction of small and medium-sized thermal power stations)

Section titled “Article 19 (Construction of small and medium-sized thermal power stations)”

The relevant institutions, enterprises and organizations shall construct small and medium-sized thermal power stations in keeping with actual conditions.

Small and medium-sized thermal power stations shall be constructed with due consideration of conditions for the supply of raw materials and industrial water, transport conditions and similar factors, so that power and heat can be used in combination and economic effectiveness can be ensured.

Article 20 (Construction of power stations using natural energy)

Section titled “Article 20 (Construction of power stations using natural energy)”

The relevant institutions, enterprises and organizations shall construct power stations using natural energy such as solar power, wind power, biomass and tidal power.

Power stations using natural energy shall be built with a long-term view, taking into account such factors as climate and geographical conditions.

Article 21 (Uniform specifications, standardization and series production of generating equipment)

Section titled “Article 21 (Uniform specifications, standardization and series production of generating equipment)”

The relevant institutions, enterprises and organizations shall apply uniform specifications and standards to small and medium-sized generating equipment and organize its production in series.

Institutions, enterprises and organizations that manufacture small and medium-sized generating equipment themselves shall manufacture it in accordance with national specifications and constantly upgrade generating equipment by actively adopting advanced science and technology.

Article 22 (Comprehensive and completion inspections of small and medium-sized power station construction)

Section titled “Article 22 (Comprehensive and completion inspections of small and medium-sized power station construction)”

Upon completion of the construction of a small or medium-sized power station, the project owners and the institutions, enterprises and organizations undertaking the construction shall carry out a comprehensive inspection and then, according to the scale of the project, obtain a completion inspection from the relevant construction supervision organ.

A small or medium-sized power station that fails the comprehensive inspection may not undergo a completion inspection, and a station that fails the completion inspection may not operate.

Chapter 3. Operation of small and medium-sized power stations

Section titled “Chapter 3. Operation of small and medium-sized power stations”

Article 23 (Basic requirement for the operation of small and medium-sized power stations)

Section titled “Article 23 (Basic requirement for the operation of small and medium-sized power stations)”

Operating small and medium-sized power stations properly is an essential requirement for normalizing power generation.

The small and medium-sized power station guidance organ and the relevant institutions, enterprises and organizations shall increase power generation by ensuring full operation and full load of the generating equipment.

Article 24 (Handing down of the power generation plan)

Section titled “Article 24 (Handing down of the power generation plan)”

The small and medium-sized power station guidance organ and the relevant institutions, enterprises and organizations shall draw up a power generation plan in line with the generating capacity of the small and medium-sized power stations and submit it to the State planning organ.

The State planning organ shall accurately calculate the generating capacity of the small and medium-sized power stations and hand down the power generation plan.

Article 25 (Fulfilment and alteration of power generation plans)

Section titled “Article 25 (Fulfilment and alteration of power generation plans)”

The relevant institutions, enterprises and organizations shall fulfil without fail the power generation plans handed down to them, month by month and quarter by quarter.

To alter a power generation plan, approval shall be obtained from the State planning organ.

Article 26 (Normalization of power generation)

Section titled “Article 26 (Normalization of power generation)”

The relevant institutions, enterprises and organizations shall modernize generating equipment, put it on a scientific basis and introduce advanced technology to maintain regular power generation at a high level.

Article 27 (Water management at small and medium-sized hydropower stations)

Section titled “Article 27 (Water management at small and medium-sized hydropower stations)”

The relevant institutions, enterprises and organizations shall maintain dams, intakes, sluice gates, waterways and similar facilities in good time, and manage water on a scientific basis to maintain a high water level and ensure the safety of structures.

They shall regularly excavate and dredge reservoirs and build or expand intakes along the route to secure more water.

Article 28 (Protection of power facilities)

Section titled “Article 28 (Protection of power facilities)”

The relevant institutions, enterprises and organizations shall plant many trees or build protective installations and the like in protection zones for small and medium-sized power stations, to protect power facilities against damage from drought, flooding, rockslides, lightning and the like.

In winter, they shall take measures such as draining water to prevent damage from cold.

Article 29 (Raising generating efficiency)

Section titled “Article 29 (Raising generating efficiency)”

The relevant institutions, enterprises and organizations shall regularly maintain and reinforce the equipment of small and medium-sized power stations to raise the generating efficiency of turbines, wind turbines and solar panels.

Inefficient equipment and technical processes shall be converted and upgraded.

The relevant institutions, enterprises and organizations shall regularly carry out equipment checks of small and medium-sized power stations, and shall find, register and eliminate defects in the equipment.

Defects that cannot be eliminated by equipment checks shall be included in the maintenance plan.

The maintenance of equipment of small and medium-sized power stations shall be divided into minor, medium and major maintenance.

The relevant institutions, enterprises and organizations shall accurately draw up the maintenance plan, keep to the maintenance cycle and maintain the operating rate of the generating equipment.

Article 32 (Scrapping, transfer and takeover of equipment)

Section titled “Article 32 (Scrapping, transfer and takeover of equipment)”

Equipment at small and medium-sized power stations may be scrapped, transferred or taken over with the approval of the central electric power industry guidance organ and the equipment management supervision organ.

The central electric power industry guidance organ and the equipment management supervision organ shall review and handle applications for approval within 30 days of receipt.

Article 33 (Keeping track of power generation figures)

Section titled “Article 33 (Keeping track of power generation figures)”

The relevant institutions, enterprises and organizations shall regularly keep track of power generation figures for small and medium-sized power stations and report them to the relevant small and medium-sized power station guidance organ and the statistical organ.

The small and medium-sized power station guidance organ shall keep track of regional power generation figures for small and medium-sized power stations and report them to the central electric power industry guidance organ.

The central electric power industry guidance organ shall keep track of nationwide power generation figures for small and medium-sized power stations and submit them periodically to the central planning guidance organ and central statistical organ.

Chapter 4. Use of power from small and medium-sized power stations

Section titled “Chapter 4. Use of power from small and medium-sized power stations”

Article 34 (Basic requirements for use of power from small and medium-sized power stations)

Section titled “Article 34 (Basic requirements for use of power from small and medium-sized power stations)”

Effective use of power generated at small and medium-sized power stations is an important undertaking for meeting the growing demand for power.

The small and medium-sized power station guidance organs and the relevant institutions, enterprises and organizations shall use power generated at small and medium-sized power stations to meet their own demand for power.

Where power generated at small and medium-sized power stations cannot meet their own demand, they may use power from the national power system.

Article 35 (Connection to the national power system)

Section titled “Article 35 (Connection to the national power system)”

Where a small or medium-sized power station is far from the place where its power is consumed, the relevant institutions, enterprises and organizations may use the power after obtaining approval from the central electric power industry guidance organ and having the relevant power transmission and distribution organ connect the station’s power system to the nearby national power system at their request. In this case, they shall comply with the power dispatching command of the central electric power industry guidance organ.

Article 36 (Formation of a power system of several small and medium-sized power stations)

Section titled “Article 36 (Formation of a power system of several small and medium-sized power stations)”

Power generated at several small and medium-sized power stations in one area may be used jointly by forming a single power system. In this case, the approval of the small and medium-sized power station guidance organ shall be obtained.

Institutions, enterprises and organizations operating small and medium-sized power stations may supply surplus power to other institutions, enterprises and organizations and to resident households, or feed it into the national power system after obtaining approval from the central electric power industry guidance organ. In this case, the institutions, enterprises and organizations that intend to use the power shall undertake the power facility works.

Article 38 (Power supply plans and contracts)

Section titled “Article 38 (Power supply plans and contracts)”

Small and medium-sized power station guidance organs shall draw up power supply plans based on the power generation plans of small and medium-sized power stations and hand them down to the relevant institutions, enterprises and organizations.

Small and medium-sized power station guidance organs and institutions, enterprises and organizations that are power end-users shall conclude and perform contracts in accordance with the power supply plans.

Institutions, enterprises and organizations that are connected to the national power system but receive a power supply plan from a small and medium-sized power station guidance organ shall conclude a contract with the relevant regional power transmission and distribution organ.

Article 39 (Calculation of power supply and consumption)

Section titled “Article 39 (Calculation of power supply and consumption)”

The small and medium-sized power station guidance organs and the relevant institutions, enterprises and organizations shall periodically verify power metering devices and accurately calculate the amounts of power actually supplied and consumed.

Article 40 (Payment of electricity charges)

Section titled “Article 40 (Payment of electricity charges)”

Institutions, enterprises, organizations and citizens that use power generated at small and medium-sized power stations shall pay the electricity charge fixed according to the quantity of power supplied.

Article 41 (Application for use of power of the national power system)

Section titled “Article 41 (Application for use of power of the national power system)”

The relevant institutions, enterprises and organizations may use power of the national power system where they cannot generate power or generate too little because of the dry season or other reasons. In this case, they shall submit approval application documents to the power transmission and distribution organ.

The power transmission and distribution organ shall examine the approval application documents within 10 days from the date of their receipt and notify the result.

Article 42 (Cutting off power of the national power system)

Section titled “Article 42 (Cutting off power of the national power system)”

An institution, enterprise or organization that temporarily uses power of the national power system shall, when the small and medium-sized power station again generates power normally, make a request to the power transmission and distribution organ and have the supply of power of the national power system cut off.

Power may not be received from two sources.

Article 43 (Use of power from small and medium-sized power stations built by cities and counties)

Section titled “Article 43 (Use of power from small and medium-sized power stations built by cities and counties)”

Use of power from small and medium-sized power stations built by cities (districts) and counties themselves shall be as prescribed by the small and medium-sized power station guidance organ.

The small and medium-sized power station guidance organ shall accurately identify the recipients of power supply and supply them with power.

The relevant institutions, enterprises and organizations shall make effective use of the power supplied by rationally organizing staggered production, converting equipment and production processes to save electricity, and lowering the unit consumption standard for power.

The relevant institutions, enterprises and organizations shall overhaul the power transmission and distribution system and eliminate the waste of power caused by losses in transit, reactive power, excessive capacity and the like.

Chapter 5. Guidance and control of the work of small and medium-sized power stations

Section titled “Chapter 5. Guidance and control of the work of small and medium-sized power stations”

Article 45 (Basic requirements for guidance and control of the work of small and medium-sized power stations)

Section titled “Article 45 (Basic requirements for guidance and control of the work of small and medium-sized power stations)”

Strengthening guidance and control of the work of small and medium-sized power stations is the basic guarantee for correctly implementing the State’s policy on the construction and operation of small and medium-sized power stations and the use of their power.

The State shall ensure that the guidance system for the work of small and medium-sized power stations is properly established and control is strengthened.

Article 46 (Guidance organ for the work of small and medium-sized power stations)

Section titled “Article 46 (Guidance organ for the work of small and medium-sized power stations)”

Guidance of the work of small and medium-sized power stations shall be exercised by the central electric power industry guidance organ under the unified guidance of the Cabinet.

The central electric power industry guidance organ shall regularly take charge of and guide the work of small and medium-sized power stations.

Article 47 (Guidance by the small and medium-sized power station guidance organ)

Section titled “Article 47 (Guidance by the small and medium-sized power station guidance organ)”

The small and medium-sized power station guidance organ shall rationally organize the work of small and medium-sized power stations of the institutions, enterprises and organizations in the area under its jurisdiction.

The relevant institutions, enterprises and organizations shall agree with the small and medium-sized power station guidance organ on, and handle, matters raised in the work of small and medium-sized power stations.

Article 48 (Supply of labour, equipment, materials and funds)

Section titled “Article 48 (Supply of labour, equipment, materials and funds)”

The State planning organ and the relevant institutions, enterprises and organizations shall provide in good time the labour, equipment, materials and funds needed to construct and operate small and medium-sized power stations.

Labour, equipment, materials and funds allocated to small and medium-sized power stations may not be diverted to other uses.

Article 49 (Supervision and control of the work of small and medium-sized power stations)

Section titled “Article 49 (Supervision and control of the work of small and medium-sized power stations)”

Supervision and control of the work of small and medium-sized power stations shall be exercised by the central electric power industry guidance organ, the small and medium-sized power station guidance organs and the relevant supervision and control organs.

The central electric power industry guidance organ, the small and medium-sized power station guidance organs and the relevant supervision and control organs shall strictly supervise and control the work of small and medium-sized power stations.

Article 50 (Control of power generation and use)

Section titled “Article 50 (Control of power generation and use)”

The small and medium-sized power station guidance organ and the relevant supervision and control organ shall control the power generation and use of small and medium-sized power stations by using modern measuring devices.

Measuring devices shall be installed at places determined by the relevant supervision and control organ.

Civil liability, such as a penalty for breach of contract or compensation for damage, shall be imposed on a party that has, by violating this Law, caused damage to other institutions, enterprises, organizations or citizens.

Institutions, enterprises, organizations and citizens shall be fined in the following cases:

  1. Where power generation figures have been falsely reported: not less than 1,000,000 won and not more than 1,500,000 won for institutions, enterprises and organizations
  2. Where power has been wasted: not less than 500,000 won and not more than 1,500,000 won for institutions, enterprises and organizations, and not less than 30,000 won and not more than 100,000 won for citizens
  3. Where power has been received from two sources: not less than 700,000 won and not more than 1,000,000 won for institutions, enterprises and organizations, and not less than 40,000 won and not more than 70,000 won for citizens

Construction or operation of small and medium-sized power stations or the use of their power shall be suspended in the following cases:

  1. Where construction is carried out under a design that has not been deliberated on and approved
  2. Where construction does not comply with the requirements of the design and construction methods
  3. Where the comprehensive and completion inspections have not been passed
  4. Where electricity charges have not been paid as prescribed

Article 54 (Penalties of warning, stern warning, unpaid labour, labour education, demotion, dismissal and removal from post)

Section titled “Article 54 (Penalties of warning, stern warning, unpaid labour, labour education, demotion, dismissal and removal from post)”

In the following cases, the person responsible shall be given the penalty of warning or stern warning, or the penalty of unpaid labour or labour education of not more than three months:

  1. Where meeting the date for putting a station into operation has been impeded by failure to ensure the quality of construction or to construct in accordance with the requirements of the design and construction methods
  2. Where a power generation plan has been underfulfilled
  3. Where power generation has been impeded by failure to properly protect power facilities or to properly inspect or repair equipment
  4. Where equipment has been scrapped or transferred without approval
  5. Where power generation figures have been falsely reported
  6. Where a power line has been connected to the national power system and power used without approval
  7. Where the calculation of power supply and consumption has not been properly carried out, or electricity charges have not been collected or paid as prescribed
  8. Where a power line has been connected to an unauthorized recipient
  9. Where power has been received from two sources
  10. Where labour, equipment, materials or funds provided to small and medium-sized power stations have been diverted to other uses
  11. Where the generation or use of power from small and medium-sized power stations has not been properly controlled, or power metering devices have not been installed at the prescribed locations

Where an act under the preceding paragraph has been committed repeatedly or has resulted in a shortfall of 20 percent or more in the power generation plan or property loss of about 20,000 won or more, the penalty of unpaid labour or labour education of not less than three months, or the penalty of demotion, dismissal or removal from post, shall be given.

Where an act in violation of this Law amounts to a crime, criminal liability shall be imposed on the person responsible in accordance with the relevant article of the Criminal Law.

English translations by NK Law are licensed under CC BY-SA 4.0.Copyright and reuse