Electric Power Law of the Democratic People's Republic of Korea
Edition dated 14 December 2023. Korean source
Adopted on 20 December Juche 84 (1995) by Decision No. 65 of the Permanent Committee of the Supreme People’s Assembly
Amended on 14 January Juche 88 (1999) by Decree No. 350 of the Standing Committee of the Supreme People’s Assembly
Amended and supplemented on 27 September Juche 90 (2001) by Decree No. 2593 of the Standing Committee of the Supreme People’s Assembly
Amended and supplemented on 24 January Juche 95 (2006) by Decree No. 1528 of the Standing Committee of the Supreme People’s Assembly
Amended and supplemented on 7 November Juche 95 (2006) by Decree No. 2045 of the Standing Committee of the Supreme People’s Assembly
Amended and supplemented on 30 September Juche 97 (2008) by Decree No. 2899 of the Standing Committee of the Supreme People’s Assembly
Amended and supplemented on 22 April Juche 104 (2015) by Decree No. 471 of the Standing Committee of the Supreme People’s Assembly
Amended and supplemented on 25 January Juche 106 (2017) by Decree No. 1521 of the Standing Committee of the Supreme People’s Assembly
Amended and supplemented on 10 May Juche 107 (2018) by Decree No. 2239 of the Standing Committee of the Supreme People’s Assembly
Amended and supplemented on 24 September Juche 107 (2018) by Decree No. 2400 of the Standing Committee of the Supreme People’s Assembly
Amended and supplemented on 20 November Juche 108 (2019) by Decree No. 163 of the Standing Committee of the Supreme People’s Assembly
Amended and supplemented on 26 November Juche 109 (2020) by Decree No. 470 of the Standing Committee of the Supreme People’s Assembly
Amended and supplemented on 26 October Juche 110 (2021) by Decree No. 756 of the Standing Committee of the Supreme People’s Assembly
Amended and supplemented on 14 December Juche 112 (2023) by Decree No. 1515 of the Standing Committee of the Supreme People’s Assembly
Korean source · NK TechLab Korean PDF, archived copy. The text comes from unchecked OCR of screenshots from a North Korean law app. Publisher’s source description
The 2023 source omits the Chapter 3 heading before Article 23. The edition marks the chapter number. The wording of the 2023 heading remains unverified.
The first draft of this translation was produced with AI assistance.
Chapter 1. Fundamentals of the Electric Power Law
Section titled “Chapter 1. Fundamentals of the Electric Power Law”Article 1 (Mission of the Electric Power Law)
Section titled “Article 1 (Mission of the Electric Power Law)”The Electric Power Law of the Democratic People’s Republic of Korea contributes to speeding up economic construction and raising the people’s living standards by strictly establishing discipline and order in power facility construction, power production, power supply, staggered production organization and command, power use, power dispatching command and operation of the national integrated power management system.
Article 2 (Principle of development of the electric power industry)
Section titled “Article 2 (Principle of development of the electric power industry)”Power is the basic motive power of the national economy.
The State shall systematically increase investment in the electric power industry sector, firmly build up independent and modern electric power industry bases, and develop the electric power industry ahead of the other sectors of the national economy.
Article 3 (Principle of power facility construction)
Section titled “Article 3 (Principle of power facility construction)”Power facility construction is the basic guarantee for strengthening the motive power base of the country.
The State shall ensure that, with hydropower station construction as the basis, the construction of thermal power stations and nuclear power stations and of power stations relying on wind, geothermal, tidal, biomass, solar heat and various other energy resources is combined with it, the construction of large-scale power stations and of small and medium-scale power stations is advanced in parallel, and the construction of transmission and distribution facilities follows on from them.
Article 4 (Principle of power production)
Section titled “Article 4 (Principle of power production)”Increasing and normalizing power production is the consistent policy of the State.
The State shall ensure that the foundation of power production is overhauled and reinforced and expanded with a long-term view, the efficiency of generating equipment is raised, and full operation and full load are maintained, so that power production increases continuously.
Article 5 (Principle of formation of the integrated power management system, power supply, staggered production organization and power use)
Section titled “Article 5 (Principle of formation of the integrated power management system, power supply, staggered production organization and power use)”The State shall ensure that, in keeping with the requirements of the development of the national economy, a State-level integrated power management system is formed and operated substantively, and that, together with this, power of good quality is supplied, staggered production is organized rationally and power is used effectively.
Article 6 (Principle of power dispatching command)
Section titled “Article 6 (Principle of power dispatching command)”The State shall ensure that a centralized power dispatching command system is established, the responsibility system of local power transmission and distribution organs is strengthened, and the operation of the power system is commanded in a unified manner.
Article 7 (Principle of modernization and automation of power facilities)
Section titled “Article 7 (Principle of modernization and automation of power facilities)”The State shall ensure that the training of scientific and technical talent and scientific research work in the electric power industry sector are strengthened, the achievements of modern science and technology are actively adopted, and power facilities are modernized and automated.
Article 8 (Principle of electricity saving and protection of power installations)
Section titled “Article 8 (Principle of electricity saving and protection of power installations)”The State shall ensure that education in patriotism is strengthened among the people, so that they use electricity as sparingly as possible and take part consciously in the work of protecting power installations.
Article 9 (Guidance of work in the power sector)
Section titled “Article 9 (Guidance of work in the power sector)”Guidance of work in the power sector shall be exercised by the central electric power industry guidance organ and the relevant central organ under the unified guidance of the Cabinet.
The central electric power industry guidance organ and the relevant central organ shall take charge of and guide work in the power sector.
Article 10 (Supervision and control of work in the power sector)
Section titled “Article 10 (Supervision and control of work in the power sector)”Supervision and control of work in the power sector shall be exercised by the central electric power industry guidance organ and the relevant supervision and control organ.
The central electric power industry guidance organ and the relevant supervision and control organ shall properly determine what is subject to power supervision and regularly exercise supervision and control so that institutions, enterprises, organizations and citizens strictly observe the rules on power facility construction, power production, power supply, staggered production organization and command, power use, power dispatching command and operation of the national integrated power management system, and strengthen electricity saving work.
Institutions, enterprises, organizations and citizens shall provide in good time the conditions needed for power supervision work.
Article 11 (Provision of working conditions for the power sector)
Section titled “Article 11 (Provision of working conditions for the power sector)”The State planning organ, electric power industry guidance organ, labour administration organs, finance organs, banking organs, local people’s committees and the relevant institutions, enterprises and organizations shall provide the power sector with the labour, equipment, fuel, materials, funds and the like it needs as a matter of priority.
Labour, equipment, fuel, materials, funds and the like for the power sector may not be diverted to other sectors, and the power sector shall not be assigned social tasks unrelated to power generation.
Article 12 (Exchange and cooperation in the field of the electric power industry)
Section titled “Article 12 (Exchange and cooperation in the field of the electric power industry)”The State shall develop scientific and technical exchange and cooperation in the field of the electric power industry with various countries of the world and international organizations, and shall encourage the construction of hydropower stations through the joint development of border rivers.
Chapter 2. Construction of power facilities
Section titled “Chapter 2. Construction of power facilities”Article 13 (Planning of power facility construction)
Section titled “Article 13 (Planning of power facility construction)”Proper construction of power facilities is an important requirement for raising power production capacity and supply capacity.
Electric power industry guidance organs and the relevant institutions, enterprises and organizations shall carry out the construction of power facilities such as power stations and transmission and distribution facilities according to plan.
Article 14 (Survey of power resources)
Section titled “Article 14 (Survey of power resources)”Electric power industry guidance organs and the relevant institutions, enterprises and organizations shall, before power facility construction, carry out a detailed survey of power resources and, on that basis, properly determine the location of power station construction.
The location for the construction of a hydropower station shall be determined with a long-term view by accurately surveying the volume of water obtainable, the head and the like, and the location for the construction of a thermal power station by accurately surveying the fuel source, its reserves, industrial water supply, the transport conditions and the like.
Article 15 (Calculation of economic effectiveness)
Section titled “Article 15 (Calculation of economic effectiveness)”Electric power industry guidance organs and the relevant institutions, enterprises and organizations shall calculate in detail the economic effectiveness of each power facility construction project and concentrate investment on projects of high economic effectiveness.
Article 16 (Drawing up of the power facility construction plan)
Section titled “Article 16 (Drawing up of the power facility construction plan)”The power facility construction plan shall be drawn up by the State planning organ.
The State planning organ shall draw up the power facility construction plan on the basis of the prospective demand for power and the data of the power resources survey.
Article 17 (Design of power facility construction)
Section titled “Article 17 (Design of power facility construction)”Designs for construction of power facilities shall be prepared by the power and motive power design institution or by the designated design institutions or enterprises.
The power and motive power design institution and the relevant design institutions and enterprises shall accurately assess the construction project and scale and similar factors, and design the power facilities in accordance with the approved technical assignment.
Designs for hydropower stations shall provide regulating reservoirs for adjusting daily loads and reserve capacity in generating equipment where needed.
Article 18 (Institutions constructing power facilities)
Section titled “Article 18 (Institutions constructing power facilities)”Power stations shall be built by specialized power station construction enterprises or the relevant institutions, enterprises and organizations.
Transmission and distribution facilities in the main power system shall be built by institutions and enterprises in the electric power industry sector. Other transmission and distribution facilities shall be built by the relevant institutions, enterprises and organizations.
Article 19 (Quality of power facility construction works and meeting the commissioning date)
Section titled “Article 19 (Quality of power facility construction works and meeting the commissioning date)”Institutions, enterprises and organizations constructing power facilities shall carry out power facility construction in accordance with the requirements of the design, raise the quality of the construction works and meet the commissioning date.
The State planning organ and the relevant institutions and enterprises shall produce and ensure the supply of generating equipment and transmission and distribution equipment in good time so that there is no impediment to the commissioning of power facilities.
Power facilities that have failed to pass the completion inspection may not be operated.
Article 20 (Construction of small and medium-sized power stations)
Section titled “Article 20 (Construction of small and medium-sized power stations)”Institutions, enterprises and organizations shall make rational use of various energy resources, build practical small and medium-sized power stations through a mass-based movement, and ensure their normal operation.
The detailed rules on the construction and operation of small and medium-sized power stations shall be governed by the laws and regulations on small and medium-sized power stations.
Article 21 (Installation, expansion and relocation of power facilities)
Section titled “Article 21 (Installation, expansion and relocation of power facilities)”Institutions, enterprises and organizations that intend to install, expand or relocate generating equipment or transmission and distribution facilities shall obtain approval from the central electric power industry guidance organ. In this case, they shall complete the procedures under the rules on use of power facilities and land.
Power lines may not be run or power poles erected indiscriminately.
Article 22 (Establishment and use of the natural energy power generation fund)
Section titled “Article 22 (Establishment and use of the natural energy power generation fund)”The State shall set up a natural energy power generation fund to provide the funds needed for the construction and management and operation of natural energy power stations.
The natural energy power generation fund shall be used only for the construction and management and operation of natural energy power stations.
Chapter 3
Section titled “Chapter 3”[The Korean source omits the Chapter 3 heading in this edition.]
Article 23 (Increasing power generation)
Section titled “Article 23 (Increasing power generation)”Power generation is one of the basic conditions for meeting the growing demand for power.
Electric power industry guidance organs and the relevant institutions, enterprises and organizations shall increase power generation by actively regulating power generation from hydro and thermal sources, repairing generating equipment and structures to a high standard, properly organizing power generation, providing the conditions for it, managing equipment, carrying out technical modifications and the like, and taking thorough measures to prevent accidents.
Article 24 (Drawing up and implementation of the power production plan)
Section titled “Article 24 (Drawing up and implementation of the power production plan)”The State planning organ shall accurately calculate the amount of power that can be produced and draw up a scientific and realistic power production plan.
Electric power industry guidance organs and the relevant institutions, enterprises and organizations shall implement the power production plan without fail.
Article 25 (Power production of hydropower stations)
Section titled “Article 25 (Power production of hydropower stations)”The relevant institutions, enterprises and organizations shall carry out the repair of hydropower station structures and generating equipment to a high standard and manage water scientifically in keeping with weather conditions, so as to normalize power production.
Article 26 (Operating efficiency of hydropower stations)
Section titled “Article 26 (Operating efficiency of hydropower stations)”The relevant institutions, enterprises and organizations shall build a system for measuring the efficiency of hydropower stations in real time and operate the stations at a high water level and high efficiency.
Generating equipment may not be operated below the dead water level. Where generating equipment is to be operated below the dead water level owing to unavoidable circumstances, the approval of the Cabinet shall be obtained.
The dead water level shall be fixed by the central electric power industry guidance organ with the approval of the Cabinet.
Article 27 (Securing water for hydropower stations)
Section titled “Article 27 (Securing water for hydropower stations)”The relevant institutions, enterprises and organizations shall newly build or expand intake facilities along the way of hydropower stations to obtain more water, regularly survey the safety of hydraulic structures and carry out inspection and repair to a high standard, so as to eliminate the loss of water in transit.
Water of the reservoir and waterways of a hydropower station may not be drawn off and used for other purposes without the approval of the central electric power industry guidance organ.
Article 28 (Protection zones of hydropower stations, waterway tunnels and reservoirs)
Section titled “Article 28 (Protection zones of hydropower stations, waterway tunnels and reservoirs)”To protect hydropower stations, waterway tunnels and reservoirs, hydropower station protection zones, waterway tunnel protection zones and reservoir protection zones shall be designated.
Hydropower station protection zones, waterway tunnel protection zones and reservoir protection zones shall be designated by the Cabinet.
Article 29 (Management of the protection zones of hydropower stations, waterway tunnels and reservoirs)
Section titled “Article 29 (Management of the protection zones of hydropower stations, waterway tunnels and reservoirs)”Institutions, enterprises and organizations managing the protection zones of hydropower stations, waterway tunnels and reservoirs, and the relevant people’s committees, shall carry out according to plan the repair of power stations and waterway tunnels, dredging of intakes, treatment of sediment at dams, excavation of spillways, dredging of reservoirs, digging of channels, creation of reservoir protection forests and the like.
Institutions, enterprises, organizations and citizens shall not discharge tailings or harmful substances into rivers flowing into hydropower station reservoirs, and where they intend to cut trees, cultivate plots or mine in a protection zone, they shall reach agreement with the central electric power industry guidance organ and obtain the approval of the central land and environment protection guidance organ and the relevant institution.
Article 30 (Power production of thermal power stations)
Section titled “Article 30 (Power production of thermal power stations)”The relevant institutions and enterprises shall overhaul and reinforce the equipment of thermal power stations, constantly renew technical and economic indicators, save fuel and increase power production.
Coal for power production shall not be used for purposes other than power production, and the consumption standards set for coal use shall be strictly observed.
Article 31 (Use of steam for power production)
Section titled “Article 31 (Use of steam for power production)”Steam for power production may not be used for other purposes, either directly or after pressure reduction.
Where, as necessary, steam for power production is to be reduced in pressure and used as industrial steam or hot water for urban heating, the approval of the Cabinet shall be obtained.
The rules on the use of industrial steam or hot water for urban heating shall be as separately prescribed.
Article 32 (Supply of coal to thermal power stations)
Section titled “Article 32 (Supply of coal to thermal power stations)”The State planning organ and the relevant institutions and enterprises shall supply the coal needed by thermal power stations ahead of other sectors, so that they can produce power with reserves of not less than one week’s worth.
The railway transport organ shall form circulating trains for the transport of coal for power production and transport the coal supplied to thermal power stations in a concentrated manner and in good time.
Coal that has not reached the prescribed grade and standard may not be supplied to thermal power stations.
Article 33 (Power production by boilers and industrial furnaces)
Section titled “Article 33 (Power production by boilers and industrial furnaces)”Institutions, enterprises and organizations that have boilers and industrial furnaces capable of producing power shall install and operate generating equipment.
Power supply to institutions, enterprises and organizations that have not installed generating equipment may be restricted.
Chapter 4. Power supply
Section titled “Chapter 4. Power supply”Article 34 (Rational supply of power)
Section titled “Article 34 (Rational supply of power)”Proper power supply is a prerequisite for firmly guaranteeing the balance between power production and consumption and maintaining the rated frequency.
Electric power industry guidance organs and the relevant institutions, enterprises and organizations shall supply the power produced rationally.
Article 35 (Power supply plan)
Section titled “Article 35 (Power supply plan)”The State planning organ shall draw up the power supply plan in accordance with the amount of power produced. In this case, the power supply plan for important production enterprises shall be drawn up in detail on the basis of ascertaining production conditions in detail each month.
Where the power produced is less than planned, or where there is an accident, natural disaster or other urgent reason, the power supply plan may be adjusted and power supplied to the relevant institutions, enterprises and organizations with the approval of the Cabinet.
Article 36 (Power supply contract)
Section titled “Article 36 (Power supply contract)”Electric power industry guidance organs and power end-user institutions, enterprises and organizations shall conclude contracts in accordance with the power supply plan and are required to perform them. In this case, power end-user institutions, enterprises and organizations shall conclude the power supply contract directly with the relevant local power transmission and distribution organ without going through a higher-level organ.
Article 37 (Power for farming and power supply in the rainy season)
Section titled “Article 37 (Power for farming and power supply in the rainy season)”Electric power industry guidance organs and the relevant institutions, enterprises and organizations shall give priority to the power needed by rural areas in the farming season, and to the supply of power in the rainy season to facilities at risk of flooding of pits, such as coal mines and mines.
Article 38 (Ensuring the quality of power)
Section titled “Article 38 (Ensuring the quality of power)”Electric power industry guidance organs and the relevant institutions, enterprises and organizations shall ensure the quality of the power they supply.
Power end-user institutions, enterprises and organizations may submit special requirements concerning the quality of the power supplied. In this case, electric power industry guidance organs and the relevant institutions, enterprises and organizations may, after examining the reasons and the capacity of transmission and distribution facilities and the like, supply power whose required quality is ensured.
Article 39 (Normal supply of power)
Section titled “Article 39 (Normal supply of power)”Electric power industry guidance organs and the relevant institutions, enterprises and organizations shall supply power normally, without interruption, in accordance with the contract.
Where power supply is to be restricted owing to overhaul and repair of power facilities or other unavoidable circumstances, or is to be suspended because of unlawful acts, the relevant institutions, enterprises and organizations shall be informed in advance.
Article 40 (Prohibition of supplying power for own consumption)
Section titled “Article 40 (Prohibition of supplying power for own consumption)”Electric power industry guidance organs and the relevant institutions, enterprises and organizations shall not supply power directly from the own-consumption power systems of power stations and substations.
Power for own consumption may be used only for power production and the operation of transmission and distribution equipment.
Article 41 (Reducing loss of power in transit)
Section titled “Article 41 (Reducing loss of power in transit)”Electric power industry guidance organs and the relevant institutions, enterprises and organizations shall reduce the loss of power in transit as far as possible by properly establishing the transmission system, reconstructing and repairing transmission and distribution networks, and raising voltage levels and the power factor.
Transmission systems shall gradually be converted to flexible alternating current transmission systems.
Article 42 (Management of power facilities)
Section titled “Article 42 (Management of power facilities)”Electric power industry guidance organs and the relevant institutions, enterprises and organizations shall regularly manage the power facilities assigned to them. In this case, they are liable for accidents that occur at the facilities they manage.
Transmission lines passing through zones where entry is restricted or prohibited shall be managed, as prescribed, by the power transmission and distribution organ or the relevant institution, enterprise or organization.
Institutions, enterprises and organizations shall provide in good time the conditions needed for the management of power facilities installed in the area under their jurisdiction.
Article 43 (Organization of assessments of the management of power facilities)
Section titled “Article 43 (Organization of assessments of the management of power facilities)”The central electric power industry guidance organ and the relevant central organ shall give guidance so that power facilities are constructed and operated in accordance with the requirements of technical regulations and the power produced is managed, and shall organize assessments of the management of power facilities every year.
Article 44 (Connection and disconnection of power facilities)
Section titled “Article 44 (Connection and disconnection of power facilities)”Institutions, enterprises and organizations that intend to connect power facilities to the national power system or disconnect power facilities from the national power system shall obtain the approval of the central electric power industry guidance organ or the relevant local power transmission and distribution organ.
Article 45 (Protection zones for transmission and distribution and power communication facilities)
Section titled “Article 45 (Protection zones for transmission and distribution and power communication facilities)”The State shall designate protection zones for transmission and distribution and power communication facilities in order to protect transmission and distribution facilities and power communication facilities.
Protection zones for transmission and distribution and power communication facilities shall be designated by the Cabinet.
Article 46 (Management of protection zones for transmission and distribution and power communication facilities)
Section titled “Article 46 (Management of protection zones for transmission and distribution and power communication facilities)”No other facilities may be constructed in protection zones for transmission and distribution and power communication facilities.
The relevant institutions, enterprises and organizations shall put up fences in those protection zones and install necessary signs such as “Electrical Hazard” and “No Entry”.
Article 47 (Protection of transmission and distribution and power communication facilities)
Section titled “Article 47 (Protection of transmission and distribution and power communication facilities)”Institutions, enterprises, organizations and citizens shall protect transmission and distribution and power communication facilities and shall not impede power supply or communication.
Power lines may not be connected without approval to transmission and distribution facilities outside one’s own system.
Chapter 5. Organization and command of staggered production
Section titled “Chapter 5. Organization and command of staggered production”Article 48 (Production and business activities under the staggered production contract)
Section titled “Article 48 (Production and business activities under the staggered production contract)”Proper organization and command of staggered production in institutions, enterprises and organizations is an important means of saving electricity and using the power produced effectively.
Power end-user institutions, enterprises and organizations shall conclude a staggered production contract with the relevant local power transmission and distribution organ and carry out production and business activities accordingly.
Institutions separately designated need not conclude staggered production contracts.
Article 49 (Preparation and submission of the staggered production schedule)
Section titled “Article 49 (Preparation and submission of the staggered production schedule)”Power end-user institutions, enterprises and organizations that intend to conclude a staggered production contract shall, in accordance with the power supply contract concluded, prepare each month a staggered production schedule that accurately incorporates the power demand by date, by hour and by machine, and then submit it to the relevant local power transmission and distribution organ within the prescribed period.
Article 50 (Requirements for preparing staggered production schedules)
Section titled “Article 50 (Requirements for preparing staggered production schedules)”Power end-user institutions, enterprises and organizations shall observe the following requirements in preparing staggered production schedules:
- They shall account for all electrical equipment used by their unit, classify it by power-consuming process and calculate hourly power consumption in each process from the equipment capacity and actual load factors.
- They shall calculate the dates and times when processes are to run and when they are to be halted, within the monthly power use limits prescribed by the power supply contract.
- They shall take into account conditions for preparing production and business activities, such as raw materials, fuel, materials, labour and equipment, and the power consumption characteristics of each piece of equipment.
Article 51 (Conclusion of the staggered production contract)
Section titled “Article 51 (Conclusion of the staggered production contract)”The local power transmission and distribution organ that has received the staggered production schedule shall, according to the power source relationship, give its agreement directly for units under its own jurisdiction, and for those under the jurisdiction of a higher-level organ submit the schedules to the higher-level organ so that its agreement is obtained.
Power end-user institutions, enterprises and organizations that have obtained agreement on the staggered production schedule shall conclude a staggered production contract with the relevant local power transmission and distribution organ.
Power shall not be supplied to power end-user institutions, enterprises and organizations that have not concluded a staggered production contract within the prescribed period, and the power end-user institution, enterprise or organization concerned is liable for this.
Article 52 (Preparation and entry of power use limits and amounts of power)
Section titled “Article 52 (Preparation and entry of power use limits and amounts of power)”A local power transmission and distribution organ that has concluded a staggered production contract with a power end-user institution, enterprise or organization shall prepare the daily and hourly power use limits and amounts of power for distribution lines, secondary substations, transmission lines and primary substations, enter them into the power management technical devices and report on the entry to the superior organ.
Article 53 (Observance of the staggered production contract)
Section titled “Article 53 (Observance of the staggered production contract)”Power end-user institutions, enterprises and organizations shall, in accordance with the staggered production contract concluded, organize staggered production rationally by workshop and work team, by process and by machine.
A staggered production contract may not be violated.
Article 54 (Change of the staggered production contract)
Section titled “Article 54 (Change of the staggered production contract)”Where the power supply plan is increased or decreased or other State requirements arise, power end-user institutions, enterprises and organizations may ask the relevant local power transmission and distribution organ to change the content of the staggered production contract.
The local power transmission and distribution organ that has received a request that the content of the staggered production contract be changed shall examine it carefully and give its agreement. In this case, a change to the staggered production schedule shall be subject to the approval of the higher-level organ or the central electric power industry guidance organ, and in special cases to the approval of the Cabinet.
Article 55 (Command of staggered production)
Section titled “Article 55 (Command of staggered production)”Electric power industry guidance organs and the relevant institutions shall regularly exercise oversight and control so that power end-user institutions, enterprises and organizations strictly observe the staggered production contract.
Power end-user institutions, enterprises and organizations shall form staggered production command teams suited to actual conditions and responsibly carry out the organization and command of staggered production in their own unit.
The staggered production command teams of ministries and central organs shall, in liaison with the central electric power industry guidance organ, properly take charge of and guide the staggered production command teams of the power end-user institutions, enterprises and organizations under them.
Chapter 6. Use of power
Section titled “Chapter 6. Use of power”Article 56 (Observance of the power supply plan and power use limits)
Section titled “Article 56 (Observance of the power supply plan and power use limits)”Using power rationally is an important means of eliminating the waste of fuel and motive power and increasing production.
Institutions, enterprises, organizations and citizens shall observe the power supply plan or power use limits and use the power supplied only for the prescribed objects.
Article 57 (Power consumption standards)
Section titled “Article 57 (Power consumption standards)”The relevant institutions, enterprises and organizations shall observe the power consumption standard per unit of product and lower it systematically.
The power consumption standard shall be set by the State planning organ or the relevant institution.
Article 58 (Remodelling of equipment and production processes)
Section titled “Article 58 (Remodelling of equipment and production processes)”The relevant institutions, enterprises and organizations shall actively conduct the technical innovation movement, introduce advanced science and technology, and remodel equipment and production processes into electricity-saving types.
The relevant scientific research institutions shall strengthen scientific research work on electricity-saving equipment and production processes.
Article 59 (Prohibition of installing excessive-capacity power equipment)
Section titled “Article 59 (Prohibition of installing excessive-capacity power equipment)”Institutions, enterprises and organizations shall not install power equipment of excessive capacity.
Installed power equipment of excessive capacity shall be replaced with power equipment of the required capacity.
Where power equipment of excessive capacity continues to be used without being replaced with power equipment of the required capacity, its operation shall be suspended.
Article 60 (Permission to use electrical equipment)
Section titled “Article 60 (Permission to use electrical equipment)”Institutions, enterprises, organizations and citizens that intend to use electrical heating equipment shall obtain permission from the central electric power industry guidance organ or the provincial power transmission and distribution organ, according to the equipment concerned. However, to use large-capacity electrical heating equipment, operate electrically heated sauna facilities or use electric heat for space heating, they shall obtain approval from the Cabinet after review by the central electric power industry guidance organ and the State planning organ.
The rules on use of other electrical equipment shall be as prescribed in the implementing regulations and detailed rules of this Law.
Article 61 (Eradication of power waste)
Section titled “Article 61 (Eradication of power waste)”Institutions, enterprises, organizations and citizens shall eliminate the idle running of machinery and equipment, and shall not operate at light load, switch on unnecessary lamps or lamps that consume much power, or use power equipment that has not been permitted or registered.
They may not engage in acts such as using power equipment contrary to its purpose and capacity, or stealthily stealing power without installing or using a power metering device or without making the wiring connection properly.
Article 62 (Compensation of reactive power)
Section titled “Article 62 (Compensation of reactive power)”Institutions, enterprises, organizations and citizens shall reduce reactive power consumption and install reactive power production equipment to compensate by themselves for the reactive power consumed.
Article 63 (Calculation of power supply and consumption and payment of power usage charges)
Section titled “Article 63 (Calculation of power supply and consumption and payment of power usage charges)”Electric power industry guidance organs shall periodically verify power metering devices and accurately calculate power supply and consumption.
Institutions, enterprises, organizations and citizens that intend to use power shall pay power usage charges to the relevant local power transmission and distribution organ as prescribed.
The procedure and method for paying power usage charges shall be as prescribed in the detailed rules for implementing this Law.
Article 64 (Supply of equipment for saving electricity)
Section titled “Article 64 (Supply of equipment for saving electricity)”The State planning organ and the relevant institutions, enterprises and organizations shall ensure, as demanded, the supply of LED lamps, reactive power production equipment, card-type integrating watt-hour meters and the like capable of saving electricity.
Article 65 (Review of electricity conservation and related measures)
Section titled “Article 65 (Review of electricity conservation and related measures)”During the electricity conservation month, electric power industry guidance organs and the relevant institutions shall conduct an intensive review of electricity conservation by institutions, enterprises and organizations, and take measures to reduce waste and loss of power.
Institutions, enterprises and organizations shall take technical measures to save electricity and develop and introduce various methods and means of doing so.
Article 66 (Prohibition of producing and importing electrical equipment of low efficiency grade)
Section titled “Article 66 (Prohibition of producing and importing electrical equipment of low efficiency grade)”Electrical equipment of low efficiency grade may not be produced or imported.
Efficiency grades for electrical equipment shall be fixed by the central electric power industry guidance organ.
Article 67 (Control of power consumption)
Section titled “Article 67 (Control of power consumption)”Electric power industry guidance organs shall verify power consumption by power-consuming units using scientific methods and strictly control power consumption.
Institutions, enterprises, organizations and citizens shall install power metering devices at places where power consumption can be verified objectively.
Chapter 7. Power dispatching command
Section titled “Chapter 7. Power dispatching command”Article 68 (Unified command of power production, supply and consumption)
Section titled “Article 68 (Unified command of power production, supply and consumption)”Power dispatching command is an important undertaking for taking charge of the operation of the power system and supplying power of good quality.
Electric power industry guidance organs shall command the processes of power production, supply and consumption in a unified manner.
Article 69 (Provision of conditions for power dispatching command)
Section titled “Article 69 (Provision of conditions for power dispatching command)”Power dispatching command may be carried out only by the dispatcher on duty.
Institutions, enterprises, organizations and citizens may not interfere with power dispatching command or violate the rules on entry into the dispatch control room.
Article 70 (Maintaining the rated frequency and prescribed voltage)
Section titled “Article 70 (Maintaining the rated frequency and prescribed voltage)”Electric power industry guidance organs shall adjust power production, supply and use to maintain the rated frequency and the prescribed voltage.
The relevant institutions, enterprises and organizations are required to obey power dispatching command.
Article 71 (Formation of the power system)
Section titled “Article 71 (Formation of the power system)”Electric power industry guidance organs shall form and operate the power system rationally so that power can be supplied to end-users in accordance with the supply plan or use limits and loss in transit can be reduced as far as possible.
Article 72 (Output-regulating power stations and fixed-output power stations)
Section titled “Article 72 (Output-regulating power stations and fixed-output power stations)”The central electric power industry guidance organ and the relevant institution shall determine output-regulating power stations and fixed-output power stations in consideration of the operational characteristics of power stations and the water and fuel supply conditions.
Output-regulating power stations shall obey the requirements of the power system.
Article 73 (Setting of power supply grades)
Section titled “Article 73 (Setting of power supply grades)”The State shall set power supply grades according to the importance and characteristics of power supply recipients and power consumers.
Power supply grades shall be set by the Cabinet.
Article 74 (Formation of the reserve power system)
Section titled “Article 74 (Formation of the reserve power system)”Electric power industry guidance organs and the relevant institutions shall supply power in accordance with the grades fixed and form reserve power systems of various types to ensure the reliability of power supply.
Article 75 (Handling of dispatching accidents and prevention of damage from natural hazards)
Section titled “Article 75 (Handling of dispatching accidents and prevention of damage from natural hazards)”Electric power industry guidance organs and the relevant institutions, enterprises and organizations shall adopt modern protection devices in the power system, properly set their setting values, handle accidents safely and prevent damage from natural hazards.
Hydrometeorological organs and the relevant institutions shall inform electric power industry guidance organs of hydrometeorological data, seismic data and the like needed to prevent damage from natural hazards.
Article 76 (Provision of power dispatching command communication)
Section titled “Article 76 (Provision of power dispatching command communication)”Electric power industry guidance organs and the relevant enterprises shall be equipped with modern communication equipment and carry out power dispatching command.
Communications organs and the relevant institutions, enterprises and organizations shall provide power dispatching command communication at the request of electric power industry guidance organs.
Article 77 (Repair of power facilities)
Section titled “Article 77 (Repair of power facilities)”Electric power industry guidance organs and the relevant institutions, enterprises and organizations shall, in consideration of the repair cycles of power equipment and the supply conditions, organize the repair of generating equipment, transmission and distribution facilities and power-using facilities simultaneously.
Chapter 8. Operation of the national integrated power management system
Section titled “Chapter 8. Operation of the national integrated power management system”Article 78 (Establishment of the national integrated power management system)
Section titled “Article 78 (Establishment of the national integrated power management system)”The national integrated power management system is a system that, under the unified command of the State, monitors, operationally controls and manages the entire process of production and consumption so that the motive power resources of the country are used rationally to maximize power production and the power produced is used effectively.
The central electric power industry guidance organ shall operate the national integrated power management system properly and ensure that voltage, frequency and waveform distortion, which are indicators of the quality of power, are maintained as prescribed.
Article 79 (Formation and operation of the national integrated power management system)
Section titled “Article 79 (Formation and operation of the national integrated power management system)”The central electric power industry guidance organ shall form the national integrated power management system of the integrated production system for hydropower stations, the integrated production system for thermal power stations and the integrated load management system, in a three-tier structure of resource planning, production management and automatic operational control, and operate it substantively.
Article 80 (Installation of power management technical devices and data communication devices)
Section titled “Article 80 (Installation of power management technical devices and data communication devices)”Institutions, enterprises and organizations that produce, supply and use power are required to install power management technical devices and data communication devices for the formation of the national integrated power management system and register them with the central electric power industry guidance organ through the relevant local power transmission and distribution organ. In this case, power management technical devices shall be deliberated on and certified by the central electric power industry guidance organ and the relevant quality certification organ.
Article 81 (Normal operation of power management technical devices and data communication devices)
Section titled “Article 81 (Normal operation of power management technical devices and data communication devices)”Institutions, enterprises and organizations that produce, supply and use power shall properly manage power management technical devices and data communication devices and ensure their normal operation.
The operation of power management technical devices and data communication devices shall be recorded every day.
Article 82 (Inspection of power management technical devices and data communication devices)
Section titled “Article 82 (Inspection of power management technical devices and data communication devices)”Institutions, enterprises and organizations that produce, supply and use power shall regularly inspect power management technical devices and data communication devices and eliminate defects in good time.
Where an abnormal problem arises in power management technical devices and data communication devices, the central electric power industry guidance organ or the relevant local power transmission and distribution organ shall be notified immediately.
Article 83 (Operation of the data communication network of the national integrated power management system)
Section titled “Article 83 (Operation of the data communication network of the national integrated power management system)”Electric power industry guidance organs and the relevant institutions, enterprises and organizations shall ensure the normal operation of the data communication network used in the national integrated power management system.
Communications organs and the relevant institutions, enterprises and organizations shall, in liaison with electric power industry guidance organs, take measures in good time against problems arising in the operation of the data communication network.
Article 84 (Security of the national integrated power management system)
Section titled “Article 84 (Security of the national integrated power management system)”The central electric power industry guidance organ and the relevant institutions, enterprises and organizations shall achieve the security of the national integrated power management system in accordance with the prescribed standards and renew it regularly.
Chapter 9. Legal liability
Section titled “Chapter 9. Legal liability”Article 85 (Civil liability)
Section titled “Article 85 (Civil liability)”Where property damage has been caused by violating this Law, civil liability such as restoration to the original state, compensation for damage or payment of a late payment charge shall be imposed on the party responsible.
Article 86 (Penalty of suspension)
Section titled “Article 86 (Penalty of suspension)”Power supply shall be suspended in the following cases:
- Where power has been used in excess of the power supply plan, use limits or power consumption standards
- Where power has been used in violation of the rules on operation of the national integrated power management system or the rules on staggered production
- Where power equipment for which permission or registration has not been obtained has been installed and used
- Where power has been used without installing or using reactive power production equipment and power metering devices, or without wiring them properly
- Where power usage charges have not been paid as prescribed
- Where power has been wasted or used through clandestine theft
- Where power supervision has been refused or obstructed
- Where power metering devices have not been installed where a power transmission and distribution organ can verify their readings objectively
- Where the risk of an accident has been created by failure to eliminate defects in power facilities in good time
- Where the cut-off circuit of a power management technical device has been disconnected without approval and power has been used
- Where a power line removed by a supervision and control organ has been connected without approval
- Where a seal suspending power use has been removed without authorization
Where power consumption standards have been exceeded or a process that consumes a large amount of power is being operated, suspension of production shall be ordered. Where refusal to comply with power supervision on grounds of special circumstances, or arbitrary issuance of documents concerning the use of power without the agreement of the relevant institutions, including the central electric power industry guidance organ, has impeded power management or supervision and control, dissolution may be ordered.
Article 87 (Dismantling of structures)
Section titled “Article 87 (Dismantling of structures)”Where a structure has been constructed without approval in a power facility protection zone in which transmission and distribution facilities, power communication facilities and the like are installed, dismantling shall be ordered.
Article 88 (Penalty of confiscation)
Section titled “Article 88 (Penalty of confiscation)”Where power equipment of excessive capacity has been installed or used without approval, or electrical equipment for which permission was not obtained has been used, the equipment, funds and goods used in or obtained through the unlawful act shall be confiscated.
Article 89 (Penalty of restitution)
Section titled “Article 89 (Penalty of restitution)”The person concerned shall be made to compensate for the damage caused in the following cases:
- Where power has been consumed without a power supply plan or without concluding power supply and staggered production contracts
- Where the hours for power use under the power supply and staggered production contracts have not been observed, or power has been consumed in excess of the supply plan
- Where power has been consumed without documents approving connection to a power source or after a power line has been connected to another transmission and distribution system without approval
- Where power has been consumed in excess of the power consumption standards
- Where power equipment of excessive capacity or electrical heating equipment has been installed or used without approval
- Where power has been consumed with power metering devices disconnected without approval or wired improperly
- Where power has been consumed without installing power metering devices and without a justifiable reason
- Where electrical equipment or products for which permission or registration has not been obtained have been used
- Where the power factor has not been maintained in accordance with the State standard
Article 90 (Penalty of a fine)
Section titled “Article 90 (Penalty of a fine)”Institutions, enterprises, organizations and citizens shall be fined the applicable amounts in the following cases:
- Where trees have been felled, land has been cultivated or mining has been undertaken without approval in protection zones for hydropower stations, water tunnels or reservoirs: 700,000 to 1,000,000 won for institutions, enterprises and organizations, and 50,000 to 100,000 won for citizens
- Where the risk of an accident has been created by failure to eliminate defects in power facilities in good time: 200,000 to 500,000 won for institutions, enterprises and organizations
- Where power supply or communication has been impeded by improper management of protection zones for transmission and distribution facilities or power communication facilities: 500,000 to 800,000 won for institutions, enterprises and organizations, and 50,000 to 100,000 won for citizens
- Where power consumption calculation data have been falsely recorded or reported: 500,000 to 800,000 won for institutions, enterprises and organizations
- Where power usage charges have not been paid in good time and accurately on improper grounds or pretexts: 300,000 to 500,000 won for institutions, enterprises and organizations, and 50,000 to 100,000 won for citizens
- Where electrical equipment that has not undergone an energy efficiency grade assessment has been produced, imported or sold: 500,000 to 1,000,000 won for institutions, enterprises and organizations
- Where the cut-off circuit of a power management technical device has been disconnected without authorization: 1,000,000 to 1,500,000 won for institutions, enterprises and organizations, and 100,000 to 200,000 won for citizens
- Where a power line removed by a supervision and control organ has been connected without authorization: 1,000,000 to 1,500,000 won for institutions, enterprises and organizations, and 100,000 to 200,000 won for citizens
- Where a seal suspending power use has been removed without authorization: 1,000,000 to 1,500,000 won for institutions, enterprises and organizations, and 100,000 to 200,000 won for citizens
- Where lawful requirements of power supervision have not been complied with: 1,200,000 to 1,500,000 won for institutions, enterprises and organizations, and 100,000 to 200,000 won for citizens
- Where supplied power has been diverted from its designated allocation and used for another purpose: 1,200,000 to 1,500,000 won for institutions, enterprises and organizations
Article 91 (Penalties of warning and stern warning)
Section titled “Article 91 (Penalties of warning and stern warning)”The person responsible shall be given the penalty of warning in the following cases:
- Where meeting the date for putting a facility into operation has been impeded by failure to ensure the quality of a power facility structure or to produce and supply equipment necessary for construction in good time
- Where land management has been impeded by running power lines or erecting power poles haphazardly
- Where power generation has been impeded by improper inspection or repair of power facilities or power equipment, or by operation of generating equipment contrary to the requirements of technical regulations and standard operating procedures
- Where generating equipment has been operated below dead water level without approval, or water has been drawn and used from a hydropower station’s reservoir or waterway without approval
- Where protection zones for hydropower stations, water tunnels or reservoirs have been improperly managed
- Where coal or steam for power generation has been used for other purposes without approval, or industrial steam or hot water for urban heating has been improperly used
- Where power generation has been impeded by failure to supply a thermal power station with coal of the prescribed grade and specifications
- Where power has been supplied to a unit with no power supply plan or that has not concluded a power supply contract
- Where power has been supplied from a system for power for own use
- Where a power line has been connected to other transmission and distribution facilities without approval
- Where power supply has been impeded by violation of the rules on organizing staggered production
- Where power has not been supplied as prescribed
- Where power has been consumed with power metering devices left uninstalled without a justifiable reason, or with improper wiring
- Where power metering devices have been disconnected without approval or actual power consumption has been omitted
- Where power usage charges have not been collected as prescribed
- Where reactive power production equipment has not been installed
- Where power supply has been impeded by improper power dispatching command, power dispatching command has been interfered with or disobeyed, or communications for power dispatching command have not been provided in good time
- Where the operation of the national integrated power management system has been impeded by improper installation or operation of power management technical devices and data communication devices
- Where the management of power facilities has been improperly assessed
- Where unlawful acts have been tolerated or encouraged in the course of power supervision
- Where lawful performance of duties by power supervisory or management personnel has been refused or obstructed
Where the circumstances of an act under the preceding paragraph are grave, the penalty of stern warning shall be given.
Article 92 (Penalties of unpaid labour and labour education)
Section titled “Article 92 (Penalties of unpaid labour and labour education)”The person responsible shall be given the penalty of unpaid labour or labour education of not more than three months in the following cases:
- Where power has been generated inefficiently by excessive consumption or waste of coal or water resources for power generation
- Where improper management of power facilities has repeatedly caused accidents in the national power system and impeded power generation or supply
- Where power equipment for which permission or registration has not been obtained has been used
- Where power supply has been suspended without a justifiable reason
- Where power facilities or power communication facilities have been damaged
- Where equipment, fuel, materials, funds or the like supplied to the power sector have been illegally disposed of
Where the circumstances of an act under the preceding paragraph are grave, the penalty of unpaid labour or labour education of not less than three months shall be given.
Article 93 (Penalties of demotion, dismissal and removal from post)
Section titled “Article 93 (Penalties of demotion, dismissal and removal from post)”Where a violation of this Law has produced grave consequences, the person responsible shall be given the penalty of demotion, dismissal or removal from post, according to the circumstances.
Article 94 (Criminal liability)
Section titled “Article 94 (Criminal liability)”Where an act in violation of this Law amounts to a crime, criminal liability shall be imposed on the person responsible in accordance with the relevant article of the Criminal Law.
Chapter 10. Supplementary provisions
Section titled “Chapter 10. Supplementary provisions”Article 95 (Date of entry into force)
Section titled “Article 95 (Date of entry into force)”The Electric Power Law, as amended and supplemented by Decree No. 1515 of the Standing Committee of the Supreme People’s Assembly of the Democratic People’s Republic of Korea [14 December Juche 112 (2023)], shall enter into force on 1 January Juche 113 (2024).