Chapter 1. Fundamentals of the Underground Railway Law

Section titled “Chapter 1. Fundamentals of the Underground Railway Law”

Article 1 (Mission of the Underground Railway Law)

Section titled “Article 1 (Mission of the Underground Railway Law)”

The Underground Railway Law of the Democratic People’s Republic of Korea contributes to ensuring the traffic convenience of the people by strictly establishing the system and order in the construction and management and operation of the underground railway.

Article 2 (Principle of developing underground railway transport)

Section titled “Article 2 (Principle of developing underground railway transport)”

The underground railway is an underground means of transport and traffic for ensuring passenger transport in cities.

The State shall ensure that underground railway transport is developed continuously by strengthening the material and technical foundation of the underground railway sector and actively adopting the achievements of modern science and technology.

Article 3 (Principle of constructing the underground railway)

Section titled “Article 3 (Principle of constructing the underground railway)”

Constructing the underground railway properly is an important requirement for completing the traffic network of cities.

The State shall ensure that the underground railway is constructed in a modern way and with a long-term view.

Article 4 (Principle of managing the underground railway)

Section titled “Article 4 (Principle of managing the underground railway)”

Underground railway management is an important undertaking that keeps the equipment and structures of the underground railway in normal working order and protects them.

The State shall ensure that the underground railway is managed scientifically and technologically and in a cultured manner.

Article 5 (Principle of operating the underground railway)

Section titled “Article 5 (Principle of operating the underground railway)”

Establishing discipline and order in underground railway operation is the basic guarantee for ensuring the accident-free operation of trains.

The State shall ensure that the underground railway operating system is properly established and that its operation is regularized and standardized.

Article 6 (Scientific research work and training of technicians and specialists)

Section titled “Article 6 (Scientific research work and training of technicians and specialists)”

The State shall ensure that scientific research work on the construction and management and operation of the underground railway is strengthened and that the necessary technicians and specialists are trained.

Article 7 (Exchange and cooperation in the underground railway sector)

Section titled “Article 7 (Exchange and cooperation in the underground railway sector)”

The State shall develop exchange and cooperation with other countries in the work of the underground railway sector.

Chapter 2. Construction of the underground railway

Section titled “Chapter 2. Construction of the underground railway”

Article 8 (Basic requirement for underground railway construction)

Section titled “Article 8 (Basic requirement for underground railway construction)”

Underground railway construction is an important undertaking for raising the passenger transport capacity of cities.

The State planning organ and the relevant institutions shall construct the underground railway according to plan.

Article 9 (Survey for underground railway construction)

Section titled “Article 9 (Survey for underground railway construction)”

The survey for underground railway construction shall be conducted by the underground railway design institution.

The underground railway design institution shall survey in detail such matters as the condition of the city, the long-term plan for urban development and the passenger flow volume corresponding to it, and the geological and hydrological conditions of the construction area.

Article 10 (Drawing up the underground railway construction plan)

Section titled “Article 10 (Drawing up the underground railway construction plan)”

The underground railway construction plan shall be drawn up by the State planning organ.

The State planning organ shall draw up the underground railway construction plan on the basis of the city construction master plan and the underground railway construction design.

Article 11 (Drawing up the underground railway construction design)

Section titled “Article 11 (Drawing up the underground railway construction design)”

The underground railway construction design shall be drawn up by the underground railway design institution.

The underground railway design institution shall draw up the design taking into consideration such matters as the survey data for underground railway construction, passenger transport capacity and the requirements of environmental protection.

The design shall obtain the approval of the relevant institution.

Article 12 (Parties undertaking underground railway construction)

Section titled “Article 12 (Parties undertaking underground railway construction)”

Underground railway construction shall be undertaken by the specialized underground railway construction institution.

Murals, sculptural decorations and the like in underground stations shall be undertaken by the relevant specialized institutions and enterprises.

Article 13 (Observance of design requirements, technical regulations and standard construction methods)

Section titled “Article 13 (Observance of design requirements, technical regulations and standard construction methods)”

The underground railway construction institution shall properly determine the order of processes in construction, strictly observe the requirements of the design, the technical regulations and the standard construction methods, and ensure the quality of construction.

Where the quality inspection is not passed, the work of the next process may not be carried out.

Article 14 (Eradication of industrial accidents)

Section titled “Article 14 (Eradication of industrial accidents)”

The underground railway construction institution shall install labour safety facilities as prescribed and prevent industrial accidents.

Where a risk of accident arises in the course of construction, it shall immediately stop work, take appropriate measures and only then carry out the work.

Article 15 (Mechanization of underground railway construction work)

Section titled “Article 15 (Mechanization of underground railway construction work)”

The underground railway construction institution shall equip itself with modern machinery and equipment and mechanize construction.

The relevant institutions and enterprises shall produce and supply in good time the machinery and equipment needed for underground railway construction.

Article 16 (Construction of underground railway structures)

Section titled “Article 16 (Construction of underground railway structures)”

Structures such as tunnels, station buildings, ventilation shafts, escalator shafts, sanitary-engineering equipment rooms and substations shall be built for the underground railway.

Depots, train inspection depots and the like may also be built underground as necessary.

Article 17 (Construction of underground railway stations)

Section titled “Article 17 (Construction of underground railway stations)”

Underground railway stations shall be built at points in the urban area where many passengers gather, taking into consideration dovetailing with surface means of transport and traffic.

Two escalator shafts or one may be built.

Article 18 (Installation of underground railway equipment)

Section titled “Article 18 (Installation of underground railway equipment)”

Escalators, signalling, electric power, communications, lighting, sanitary-engineering equipment and the like for operation shall be installed in the underground railway.

Equipment that is economically and technically backward or conflicts with the requirements of environmental protection may not be installed.

When underground railway construction is finished, a completion inspection shall be carried out.

The underground railway that has passed the completion inspection shall be handed over to the underground railway operating organ. In this case, such items as the technical documents needed for the management and operation of the underground railway shall be handed over together.

Chapter 3. Management of the underground railway

Section titled “Chapter 3. Management of the underground railway”

Article 20 (Basic requirement for underground railway management)

Section titled “Article 20 (Basic requirement for underground railway management)”

Managing the underground railway properly is an essential requirement for raising the utilization rate of the underground railway and ensuring its cultured quality.

The underground railway operating organ shall accurately apportion the management of the equipment and structures of the underground railway and manage them regularly.

The underground railway operating organ shall periodically inspect the technical condition of underground railway equipment.

Underground railway equipment that has not passed the inspection may not be operated.

Underground railway equipment that is newly received or repaired may be operated only after it has passed a trial run.

Technical servicing of underground railway equipment shall be carried out according to a cycle.

The technical servicing cycle shall be fixed by the underground railway operating organ.

Intensive servicing of underground railway equipment shall be carried out once a month.

The underground railway shall not be operated on the day of intensive servicing of equipment.

The underground railway operating organ and the relevant institutions and enterprises shall build up repair bases solidly and repair underground railway equipment according to plan.

Repair of underground railway equipment shall be divided into major repair, medium repair and minor repair.

Article 25 (Ensuring the quality of repair and meeting time limits)

Section titled “Article 25 (Ensuring the quality of repair and meeting time limits)”

The underground railway operating organ and the institutions and enterprises commissioned to repair underground railway equipment shall duly observe the prescribed repair processes, ensure the quality of repair and meet the time limits for repair.

The underground railway operating organ and the relevant institutions and enterprises shall carry out the maintenance of underground railway structures properly and ensure the cultured quality and safety of the underground railway.

Maintenance of underground railway structures shall be divided into major maintenance and minor maintenance.

The relevant underground railway station shall not be operated during the period of major maintenance.

Article 27 (Management of trains and underground railway stations)

Section titled “Article 27 (Management of trains and underground railway stations)”

The underground railway operating organ shall keep trains and underground railway stations in a hygienic and cultured manner, manage them cleanly and disinfect them periodically.

Article 28 (Ventilation shaft protection zone)

Section titled “Article 28 (Ventilation shaft protection zone)”

The State shall fix a ventilation shaft protection zone to protect the ventilation shafts of the underground railway.

The ventilation shaft protection zone shall be fixed by the Cabinet.

Article 29 (Prohibited acts in the ventilation shaft protection zone)

Section titled “Article 29 (Prohibited acts in the ventilation shaft protection zone)”

Institutions, enterprises, organizations and citizens shall not enter the ventilation shaft protection zone without approval or commit acts such as constructing in the protection zone buildings and facilities that impede ventilation and the protection of the shafts.

Article 30 (Ensuring access for underground railway personnel)

Section titled “Article 30 (Ensuring access for underground railway personnel)”

Underground railway personnel may enter the necessary places of the relevant institutions, enterprises and organizations in order to maintain ventilation shafts or service underground railway equipment.

The relevant institutions, enterprises and organizations shall ensure access for underground railway personnel for the maintenance of ventilation shafts or the servicing of equipment.

Article 31 (Mass-based protection of the underground railway)

Section titled “Article 31 (Mass-based protection of the underground railway)”

The underground railway operating organ and the relevant institutions, enterprises and organizations shall strengthen education in socialist patriotism among the people and ensure that they take an active part in the work of protecting the underground railway.

Citizens shall immediately inform the relevant institution when an abnormality arises in the equipment and structures of the underground railway or when they discover an act that impedes the management and operation of the underground railway.

Chapter 4. Operation of the underground railway

Section titled “Chapter 4. Operation of the underground railway”

Article 32 (Basic requirement for underground railway operation)

Section titled “Article 32 (Basic requirement for underground railway operation)”

Discipline is the lifeblood of underground railway operation.

The underground railway operating organ shall establish a monolithic dispatch command system and ensure the accident-free operation of trains.

The underground railway operating organ shall draw up the train timetable accurately and ensure that trains are operated according to the timetable.

The train timetable may not be altered or breached at will.

Trains shall be driven only by locomotive drivers holding the required qualifications.

Locomotive drivers shall strictly observe the requirements of the technical regulations and the standard operating procedures in driving trains.

Trains may not be driven without an assistant locomotive driver.

Article 35 (Maintaining the train operation interval)

Section titled “Article 35 (Maintaining the train operation interval)”

The train dispatcher, the driving supervisor and the locomotive driver shall maintain the prescribed train operation interval.

Where the interval timer or the interval indicator breaks down, the driving supervisor shall inform the locomotive driver of the relevant interval and take repair measures in good time.

The underground railway operating organ shall ensure the normal operation of escalators and run all the escalators during hours of heavy passenger traffic volume.

During hours of exceptionally heavy passenger traffic volume, the separately prescribed rules shall be followed.

Article 37 (Ventilation and accident prevention measures)

Section titled “Article 37 (Ventilation and accident prevention measures)”

The underground railway operating organ shall keep the ventilation equipment in normal operation and ensure clear and clean air in the underground railway.

Fire-fighting equipment shall be installed in underground railway stations and the prescribed places, and accident prevention measures shall be taken.

Article 38 (Operating hours of the underground railway)

Section titled “Article 38 (Operating hours of the underground railway)”

The underground railway operating organ shall observe the prescribed operating hours. However, where passenger traffic volume is exceptionally heavy, the prescribed operating hours may be extended.

The operating hours of the underground railway shall be fixed by the Cabinet.

Article 39 (Public notice of underground railway operation)

Section titled “Article 39 (Public notice of underground railway operation)”

Where the underground railway operating hours have been changed or the underground railway cannot be operated owing to intensive servicing or major maintenance, the underground railway operating organ shall give public notice in good time at the surface stations of the underground railway.

The underground railway operating organ shall raise service-mindedness towards passengers and ensure that they consciously observe the rules on the use of the underground railway.

Where underground railway operation is temporarily suspended owing to an accident or other circumstances, it shall immediately inform passengers of such matters as the expected operating time and take appropriate measures in good time.

Article 41 (Compliance with the requirements of underground railway personnel)

Section titled “Article 41 (Compliance with the requirements of underground railway personnel)”

Passengers using the underground railway shall not obstruct underground railway personnel in the performance of their duties and shall comply with their requirements for establishing order in the use of the underground railway.

Article 42 (Ensuring convenience in using the underground railway)

Section titled “Article 42 (Ensuring convenience in using the underground railway)”

The underground railway operating organ shall ensure the convenience of passengers by installing direction signs, general information boards and the like in underground stations.

It shall make the sanitary facilities of underground stations available for use during the operating hours of the underground railway.

Underground railway tickets shall be sold at the surface stations of the underground railway.

The hours of selling underground railway tickets shall be fixed to be the same as the operating hours of the underground railway.

Article 44 (Use of the underground railway by ticket)

Section titled “Article 44 (Use of the underground railway by ticket)”

Citizens shall use the underground railway by paying with an underground railway ticket.

The underground railway may not be used by paying with money, bus tickets or the like.

Article 45 (Prohibited acts in the underground railway)

Section titled “Article 45 (Prohibited acts in the underground railway)”

Citizens shall not, in the underground railway, commit acts such as damaging equipment and buildings, smoking or spitting, or use the underground railway carrying baggage that impedes the management and operation of the underground railway.

Article 46 (Commercial service activities in underground railway stations)

Section titled “Article 46 (Commercial service activities in underground railway stations)”

The underground railway operating organ may conduct in underground railway stations commercial service activities needed to ensure the convenience of passengers. In this case, it shall obtain the approval of the central commerce guidance organ.

Chapter 5. Guidance and control of work in the underground railway sector

Section titled “Chapter 5. Guidance and control of work in the underground railway sector”

Article 47 (Basic requirement for guidance and control of work in the underground railway sector)

Section titled “Article 47 (Basic requirement for guidance and control of work in the underground railway sector)”

Strengthening guidance and control of work in the underground railway sector is an important means of correctly implementing the State’s transport and traffic policy.

The State shall ensure that the guidance system for work in the underground railway sector is properly established and that control is strengthened.

Article 48 (Guidance organ for work in the underground railway sector)

Section titled “Article 48 (Guidance organ for work in the underground railway sector)”

Guidance of work in the underground railway sector shall be exercised by the underground railway guidance organ under the unified guidance of the Cabinet.

The underground railway guidance organ shall regularly take charge of and guide work in the underground railway sector.

Article 49 (State support and favourable treatment)

Section titled “Article 49 (State support and favourable treatment)”

The State shall establish a social climate of actively helping the underground railway sector and shall accord special favourable treatment to the personnel working in this sector.

Article 50 (Supply of labour, equipment, materials and funds)

Section titled “Article 50 (Supply of labour, equipment, materials and funds)”

The State planning organ and the relevant institutions shall ensure in good time the supply of the labour, equipment, materials and funds needed for the underground railway sector.

The electric power supply organ shall regularly supply good-quality electric power needed for work in the underground railway sector.

The underground railway operating organ and the relevant institutions shall set up a regular inspection and maintenance system for electric power facilities and equipment, wage the technical innovation movement actively and reduce electric power loss as far as possible.

The city management organ shall regularly supply the water needed for the management and operation of the underground railway.

The underground railway operating organ shall carry out the servicing of water supply pipes and the management of water tanks properly and use water effectively in the management and operation of the underground railway.

Article 53 (Supervision and control organs for work in the underground railway sector)

Section titled “Article 53 (Supervision and control organs for work in the underground railway sector)”

Supervision and control of work in the underground railway sector shall be exercised by the underground railway guidance organ and the relevant supervision and control organ.

The underground railway guidance organ and the relevant supervision and control organ shall regularly supervise and control the construction and management and operation of the underground railway.

Article 54 (Suspension of command and suspension of qualification)

Section titled “Article 54 (Suspension of command and suspension of qualification)”

Where the train operation interval has been gravely violated through errors in underground railway train operation command, driving command or driving operation, or inconvenience has been caused to passengers through failure to operate equipment properly, the relevant command shall be suspended or the qualification shall be suspended.

Article 55 (Restoration to the original state and compensation for damage)

Section titled “Article 55 (Restoration to the original state and compensation for damage)”

Where equipment or buildings of the underground railway have been damaged or destroyed, the offender shall be made to restore them to the original state or to compensate for the damage caused.

Article 56 (Fine and removal from the underground railway station)

Section titled “Article 56 (Fine and removal from the underground railway station)”

Where the rules on the use of the underground railway have been violated or the management and operation of the underground railway has been impeded, the offender shall be fined or removed from the underground railway station.

Article 57 (Administrative or criminal liability)

Section titled “Article 57 (Administrative or criminal liability)”

Administrative or criminal liability shall be imposed, according to the circumstances, on the officials responsible in institutions, enterprises and organizations, and on individual citizens, who, by violating this Law, have caused serious consequences for work in the underground railway sector.