Law of the Democratic People's Republic of Korea on Construction Supervision

Edition dated 8 October 2020. August 2024 NIS compilation, vol. 2, pp. 36–41

Adopted on 10 July Juche 103 (2014) by Decree No. 80 of the Standing Committee of the Supreme People’s Assembly
Amended and supplemented on 23 November Juche 105 (2016) by Decree No. 1421 of the Standing Committee of the Supreme People’s Assembly
Amended and supplemented on 8 October Juche 109 (2020) by Decree No. 438 of the Standing Committee of the Supreme People’s Assembly

Source · Republic of Korea National Intelligence Service, Compilation of North Korean Laws (북한법령집), August 2024, vol. 2, pp. 36–41.

The first draft of this translation was produced with AI assistance.

Chapter 1. Fundamentals of the Law on Construction Supervision

Section titled “Chapter 1. Fundamentals of the Law on Construction Supervision”

Article 1 (Mission of the Law on Construction Supervision)

Section titled “Article 1 (Mission of the Law on Construction Supervision)”

The Law of the Democratic People’s Republic of Korea on Construction Supervision, by strictly establishing the system and order in construction supervision procedures and methods and in the handling of construction supervision results, contributes to guaranteeing the safety and quality of completed construction work, eliminating unlawful construction acts and ensuring that construction is carried out according to plan.

Article 2 (Principle of establishing the construction supervision system)

Section titled “Article 2 (Principle of establishing the construction supervision system)”

Properly establishing the construction supervision system is an important requirement for preventing unlawful acts in construction and raising the quality of completed construction work.

The State shall establish in good order a unified construction supervision and control system and ensure that the construction laws and regulations are strictly observed.

Article 3 (Principle of handling construction supervision results)

Section titled “Article 3 (Principle of handling construction supervision results)”

The State shall ensure scientific character, objectivity, fairness and prudence in the handling of construction supervision results.

Article 4 (Principle of heightening the sense of responsibility and increasing the role of construction supervision personnel)

Section titled “Article 4 (Principle of heightening the sense of responsibility and increasing the role of construction supervision personnel)”

The State shall ensure that the ranks of construction supervision personnel are firmly built up, their sense of responsibility is heightened and their role increased.

Construction supervision may be carried out only by officials who hold the required qualifications and have construction supervision authority.

Matters concerning construction supervision work for which this Law lays down no rules shall be governed by the relevant laws and regulations.

Chapter 2. Construction supervision procedures and methods

Section titled “Chapter 2. Construction supervision procedures and methods”

Article 6 (Buildings and facilities subject to construction supervision and methods of supervision)

Section titled “Article 6 (Buildings and facilities subject to construction supervision and methods of supervision)”

Construction supervision shall be carried out, by means of regular supervision and concentrated supervision, on buildings and facilities that are newly constructed or are extended, rebuilt, relocated and rebuilt, enlarged, reconstructed, restored or given major repair.

Article 7 (Dispatch of construction supervision inspectors)

Section titled “Article 7 (Dispatch of construction supervision inspectors)”

The construction supervision organ shall dispatch construction supervision inspectors, according to supervision jurisdiction, to projects for which a construction permit has been obtained.

Construction supervision inspectors shall be dispatched to important construction projects by the State construction supervision organ.

Article 8 (Assignment of inspectors, and organization and operation of quality inspection committees)

Section titled “Article 8 (Assignment of inspectors, and organization and operation of quality inspection committees)”

The construction client and the contractor institutions, enterprises and organizations shall assign capable inspectors to the construction site, organize a quality inspection committee of the relevant officials and operate it effectively, and thereby guarantee the quality of construction work process by process.

The construction supervision organ shall supervise the assignment and activities of the inspectors of the construction client and the construction contractor, and the organization and operation of the quality inspection committees.

Article 9 (Setting up and management of the construction site, and site area clearing)

Section titled “Article 9 (Setting up and management of the construction site, and site area clearing)”

Contractor institutions, enterprises and organizations shall, as prescribed, set up the construction site, provide safe, cultured and hygienic working and living conditions for builders, and protect the surrounding environment.

The construction supervision organ and the relevant institution shall supervise the demolition of unnecessary buildings and facilities within the construction plot, the installation of temporary structures and facilities for the works and of fences, the labour safety and environmental protection measures taken, site area clearing after the works are completed, and the like.

Article 10 (Process-by-process deliberation)

Section titled “Article 10 (Process-by-process deliberation)”

The construction supervision organ shall establish a process-by-process deliberation system suited to the scale and characteristics of the construction project and the stage of the works, and shall deliberate on whether the technical design has been drawn up in conformity with the endorsed layout plan, the design proposal and the design engineering requirements, whether domestically produced finishing materials have been incorporated, and whether materials, equipment, formwork, machines and tools suited to the construction method have been prepared, among other matters.

Process-by-process deliberation shall be conducted, before the process concerned is carried out, at the construction site, involving officials of the relevant institutions including those of construction supervision, design, quality supervision, the construction client, contractor institutions, enterprises and organizations.

A process that has not undergone process-by-process deliberation may not be carried out as construction work, and process inspection and confirmation of work done may not be conducted for it.

Article 11 (Use of materials, equipment and installations in construction work)

Section titled “Article 11 (Use of materials, equipment and installations in construction work)”

The relevant institutions, enterprises and organizations shall, when purchasing construction materials, equipment and installations, accurately conduct quality inspection and acceptance inspection, and use in construction work only products that have passed inspection.

The construction supervision organ shall inspect whether the specifications of materials, equipment and installations used in construction work, including cement, steel and aggregate, conform to the design and construction standards, and strictly supervise so that only those that have passed are used.

Article 12 (Process inspection method and assessment)

Section titled “Article 12 (Process inspection method and assessment)”

Process inspection shall consist of the construction supervision inspector finally confirming processes that the construction contractor’s inspectors, the construction client’s inspectors and the quality inspection committee have inspected and confirmed. In this case the construction supervision inspector shall examine whether construction work was carried out as decided at the process-by-process deliberation and whether the design, the construction standards and the requirements of the construction method were observed, and, using inspection instruments and tools suited to the characteristics of the construction process concerned, shall inspect scientifically and technologically whether the inspection indicators have reached the prescribed standards.

Where a process passes the process inspection, a certificate of passing the process inspection shall be issued, and for a process that has failed, the defects to be eliminated and the time allowed to eliminate them shall be specified.

Where a process has not passed the process inspection, works of the next process may not be carried out.

Article 13 (Confirmation of work done, supervision of material consumption and assessment of quality grade)

Section titled “Article 13 (Confirmation of work done, supervision of material consumption and assessment of quality grade)”

The construction supervision organ shall give confirmation of work done on the basis of the process inspection results and shall strictly supervise material consumption. In this case, confirmation of work done shall be given only for processes for which a certificate of passing the process inspection has been issued.

Where all processes included in the works or section concerned have passed inspection, the construction supervision organ shall assess the quality grade for each work.

The construction client and the contractor institutions, enterprises and organizations shall conduct an interim inspection at the prescribed construction work stages, or where the construction client or the construction contractor is replaced or works that had been suspended for a certain period resume.

The construction supervision organ shall supervise so that the construction client and contractor institutions, enterprises and organizations conduct interim inspections properly, and shall conduct an interim inspection where, in the course of the works, a need arises to inspect the overall condition of construction work on the construction project and take measures.

At the interim inspection, the results of the process inspection and the quality grade assessment and the overall condition of construction work shall be reconfirmed and appropriate measures shall be taken.

The construction supervision organ shall take part in the comprehensive inspection and supervise so that the construction contractor and the construction client institutions and enterprises conduct the comprehensive inspection properly.

Where the construction project has not undergone the comprehensive inspection or has not passed it, an application for completion inspection may not be made.

Institutions, enterprises and organizations that wish to undergo completion inspection shall submit a written application for completion inspection to the relevant construction supervision organ.

The construction supervision organ that has received the written application for completion inspection shall organize a completion inspection committee and conduct an inspection of the quality of the completed construction work and its operational readiness.

No one may use completed construction work that has not undergone completion inspection or has not passed it.

Procedures for completion inspection shall be governed by the relevant laws and regulations.

Article 17 (Quality guarantee of completed construction work)

Section titled “Article 17 (Quality guarantee of completed construction work)”

The relevant institutions, enterprises and organizations shall guarantee the quality of completed construction work for the prescribed period.

For an accident occurring during the quality guarantee period of completed construction work, the relevant institution, enterprise or organization is liable according to the results of the technical examination by the construction supervision organ.

Article 18 (Supervision of unlawful construction acts)

Section titled “Article 18 (Supervision of unlawful construction acts)”

The construction supervision organ shall supervise the following unlawful construction acts:

  1. Constructing when any of the following is missing: the approved master plan for construction, the construction specification document, the construction design, the construction plan or the construction permit documents
  2. Constructing contrary to the approved master plan for construction, construction specification document or construction design
  3. Carrying out design and construction work not in conformity with the prescribed standards
  4. Arbitrarily determining the construction contractor, or contracting out the construction to an individual, contrary to the construction plan or construction permit
  5. Having existing completed construction work demolished, or setting up a construction site, without obtaining a construction permit
  6. Causing completed construction work that has not undergone completion inspection or has not passed it to be put into operation or used, or putting it into operation or using it
  7. Using or selling temporary structures for the works without removing them in good time after the construction of the project is completed
  8. Other acts of constructing in violation of legal requirements

Article 19 (Duty to undergo construction supervision)

Section titled “Article 19 (Duty to undergo construction supervision)”

Institutions, enterprises and organizations carrying out construction are required to undergo supervision and control by the construction supervision organ.

Institutions, enterprises and organizations may neither carry out construction nor receive funds unless they undergo supervision and control by the construction supervision organ.

Institutions, enterprises, organizations and citizens shall not connive at or encourage unlawful construction acts, or disobey or interfere with construction supervision and control.

Chapter 3. Handling of construction supervision results

Section titled “Chapter 3. Handling of construction supervision results”

Article 20 (Drawing up of the record of the violation of law)

Section titled “Article 20 (Drawing up of the record of the violation of law)”

Where the construction supervision organ finds an unlawful act in the course of construction supervision, it may obtain a record or a written confirmation from the offender or the person concerned.

The unlawful facts and the necessary particulars shall be stated in detail in the record and the written confirmation.

Where the construction supervision organ and the relevant institution find a defect in the course of deliberation on the master plan for construction and the construction design, supervision of construction work or completion inspection, they may demand that the relevant institution, enterprise or organization eliminate it.

The relevant institution, enterprise or organization shall eliminate the identified defect in good time and inform the construction supervision organ or the relevant institution.

Where a defect appears in the course of construction and it is considered that it must be corrected, the construction supervision organ shall suspend the work and take appropriate measures.

Article 23 (Submission of the record of the violation)

Section titled “Article 23 (Submission of the record of the violation)”

Where construction supervision personnel intend to give a penalty for an unlawful act found in the course of supervision, they shall submit the record of the violation to the relevant institution.

The record of the violation shall state the necessary particulars such as the name of the violator of the law, his or her workplace and position, and the unlawful facts.

Article 24 (Deliberation and decision on the record of the violation)

Section titled “Article 24 (Deliberation and decision on the record of the violation)”

Deliberation and decision on the record of the violation shall be made at the council of officials in charge of the relevant institution.

The relevant institution shall deliberate and decide within the prescribed period from the date of receipt of the submitted record of the violation.

Article 25 (Referral of the record of the violation)

Section titled “Article 25 (Referral of the record of the violation)”

Where the construction supervision organ considers that, for an unlawful act found in the course of supervision, a penalty beyond its authority must be given, it shall hand the record of the violation over to a competent administrative penalty organ or law enforcement organ.

The record of the violation shall be referred by drawing up a written decision on referral of the record of the violation and sending it to the relevant institution with the corresponding record of the violation of law attached.

Article 26 (Complaints and their handling)

Section titled “Article 26 (Complaints and their handling)”

Institutions, enterprises, organizations and citizens that have a grievance concerning construction supervision work may lodge a complaint with the construction supervision organ or the relevant institution.

The institution that has received a complaint shall ascertain the facts and handle the complaint correctly within the prescribed period.

Chapter 4. Guidance and control of construction supervision work

Section titled “Chapter 4. Guidance and control of construction supervision work”

Article 27 (Guidance of construction supervision work)

Section titled “Article 27 (Guidance of construction supervision work)”

Guidance of construction supervision work shall be exercised by the relevant construction supervision guidance organ and local people’s committees under the unified guidance of the Cabinet.

The Cabinet, the relevant construction supervision guidance organ and local people’s committees shall regularly take charge of and guide construction supervision.

Article 28 (Provision of conditions for construction supervision work)

Section titled “Article 28 (Provision of conditions for construction supervision work)”

The construction supervision organ may demand that the relevant institutions, enterprises, organizations and citizens provide conditions for construction supervision work. In this case, institutions, enterprises, organizations and citizens shall provide in good time the data necessary for construction supervision, including design documents, and the working conditions.

Article 29 (Supervision and control of construction supervision work)

Section titled “Article 29 (Supervision and control of construction supervision work)”

Supervision and control of construction supervision work shall be exercised by the relevant supervision and control organ.

The relevant supervision and control organ shall regularly supervise and control the implementation of the State’s construction supervision policy.

Where damage has been caused to institutions, enterprises, organizations and citizens in violation of this Law, the offender shall be made to compensate for the damage caused.

Article 31 (Administrative and criminal liability)

Section titled “Article 31 (Administrative and criminal liability)”

Administrative or criminal liability shall be imposed, according to the circumstances, on the officials responsible in institutions, enterprises and organizations and on individual citizens for violations of this Law that cause serious consequences.